Home›Featured›First Power Flows from Biggest US Offshore Wind Farm
First Power Flows from Biggest US Offshore Wind Farm

Share this article

The Coastal Virginia Offshore Wind (CVOW) project, being built by Dominion Energy off Virginia Beach, has produced first power.

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

FeaturedHeadlinesFixed-BottomProject UpdatesWind Farm Update

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Related articles

Clarksons Wins Port & Agency Services Contract for OranjeWind Offshore Wind Farm
Ports & Logistics

Clarksons Wins Port & Agency Services Contract for OranjeWind Offshore Wind Farm

13 days ago

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free

Related news

Clarksons Wins Port & Agency Services Contract for OranjeWind Offshore Wind Farm
Ports & Logistics

Clarksons Wins Port & Agency Services Contract for OranjeWind Offshore Wind Farm

13 days ago

“Today, CVOW delivered its first power to the grid—right on schedule. This achievement marks another important step forward, adding much‑needed electricity to help meet the fastest‑growing power demand in the country” , Robert Blue , CEO at Dominion Energy, said on 23 March via social media. “This project is a critical part of Virginia’s all‑of‑the‑above energy strategy. As additional turbines are installed, CVOW will continue delivering more power on the path to full completion early next year.”

The first of CVOW’s 176 Siemens Gamesa 14 MW wind turbines was installed in January by Charybdis , the first Jones Act-compliant wind turbine installation vessel (WTIV), commissioned by Dominion Energy and built at Seatrium’s AmFELS shipyard in Brownsville, Texas.

Related Article

First Turbine Up at Biggest US Offshore Wind Farm

Offshore construction on the Coastal Virginia Offshore Wind project started in 2024.

On 22 December 2025, the project was issued a stop-work order by the US government, together with four other offshore wind farms under construction. Dominion Energy filed for a temporary restraining order and an injunction in the US District Court for the Eastern District of Virginia on 23 December, and was granted a preliminary injunction on 16 January, which allowed the construction to continue.

Related Article

Court Allows Construction of Biggest US Offshore Wind Farm to Continue

Once fully commissioned in early 2027, CVOW will become the biggest US offshore wind farm and, with an installed capacity of 2.6 GW, one of the biggest in the world today.

Reach the offshore wind industry in one go!

offshoreWIND.biz is read by thousands of offshore wind professionals every day.

—

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our offshore wind business directory.

Follow offshoreWIND.biz on:

Featured

March 24, 2026 · about 4 months ago

First Power Flows from Biggest US Offshore Wind Farm

The Coastal Virginia Offshore Wind (CVOW) project, being built by Dominion Energy off Virginia Beach, has produced first power. “Today, CVOW delivered its first power to the grid—right on schedule. This achievement marks another important step forward, adding much‑needed electricity to help meet the

2 minutes read
  • LinkedIn
  • X
  • Email

Trending Now

  1. 1Cadeler Adds Wind Ace to Fleet, First Stop East Anglia Two
  2. 2Turbine Installation at Thor Offshore Wind Farm Reaches Halfway Point
  3. 3South Korean Cable Maker Takes Delivery of Its Second Cable Laying Vessel
  4. 4Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team