According to a social media post from Heerema Marine Contractors on 31 March, both the jacket and the topside are now in place, with the project’s second substation (OCS2) to be installed later this year.
Heerema Fabrication Group, which was contracted in 2022 by Aibel to design and fabricate jackets for the two Hornsea 3 OCS platforms, said on 24 March that it had completed the foundation for the first offshore substation, and that the substructure was towed to SSCV Sleipnir on 18 March.