By February this year, twelve jackets were in place, with 20 new foundations added since then, according to Ocean Winds, which owns the 496 MW project in a joint venture with Sumitomo Corporation and Banque des Territoires.
The jacket foundations are being delivered by a consortium of Navantia Seanergies and Windar Renovables from their facilities in Spain. The four-legged jackets were manufactured at Navantia Seanergies factory in Fene, while the pin piles were produced by Windar Renovables in Avilés.