The developer is seeking a court injunction after GE Vernova notified the company that it would terminate the contract at the end of April, with Vineyard Wind seeking to make the supplier continue its work on the project.
GE Vernova cites Vineyard Wind withholding payments for completed work as grounds for terminating the contracts.