Jan De Nul has completed the installation of two export cables for the Fengmiao 1 offshore wind farm, being built by Copenhagen Infrastructure Partners (CIP) 35 kilometres off the coast of Taichung, Taiwan. The two high-voltage subsea cables, measuring 45 kilometres and 44 kilometres, have been inst