A judge at the Suffolk County Superior Court in Massachusetts has denied GE Vernova’s appeal in a case in which Vineyard Wind was recently granted a preliminary injunction that leaves the wind turbine OEM on the Vineyard Wind 1 offshore wind project until its completion.
Earlier this year, Vineyard Wind, a joint venture between Avangrid and Copenhagen Infrastructure Partners (CIP), filed a motion for a preliminary injunction after receiving a contract termination notice from GE Vernova, arguing that the turbine supplier was attempting to exit the project at a critical stage.