Germany’s Federal Maritime and Hydrographic Agency (BSH) has launched a second amendment procedure for the country’s 2025 Offshore Site Development Plan (Flächenentwicklungsplan/FEP), proposing several changes to offshore wind areas, auction schedules and grid connection plans in the North Sea.
The draft amendment, published on 19 June , includes revised planning options for offshore wind sites N-10.1 and N-10.2, which were put out to tender in 2025 and received no bids, adjustments to the timing of auctions and commissioning dates for several areas, changes to the boundaries of sites N-12.5 and N-12.6, and modifications to the route of the NOR-10-1 offshore grid connection.