Preparations for the installation of inter-array cables at the Neart na Gaoithe offshore wind farm site, located some 15 kilometers off the Fife coast in Scotland, have been completed while several other offshore activities are ongoing, including the pile installation for the jacket foundations being performed by the Saipem 3000 crane vessel.
Helix Robotics Solutions, contracted for UXO identification and removal and boulder clearance, completed the final boulder clearance campaign along the inter-array cable routes this month. The company used the vessel Sartor for the work, which was replaced by other vessels a couple of times since the beginning of the work in early April.