Home›Grid Connection›TenneT Says Damage to Hollandse Kust Zuid Beta Jacket ‘Limited’, Topside Installation a Go
Grid Connection

March 24, 2022 · about 4 years ago

TenneT Says Damage to Hollandse Kust Zuid Beta Jacket ‘Limited’, Topside Installation a Go

The installation of the Hollandse Kust Zuid Beta offshore substation topside will not be affected by the damage the substation’s jacket foundation suffered in a recent collision with a cargo ship, TenneT said. As reported, the cargo ship Julietta D collided with the substation jacket and a turbine f

2 minutes read
  • LinkedIn
  • X
  • Email
TenneT Says Damage to Hollandse Kust Zuid Beta Jacket ‘Limited’, Topside Installation a Go

The installation of the Hollandse Kust Zuid Beta offshore substation topside will not be affected by the damage the substation’s jacket foundation suffered in a recent collision with a cargo ship, TenneT said.

As reported, the cargo ship Julietta D collided with the substation jacket and a turbine foundation at the Hollandse Kust Zuid wind farm in the Dutch North Sea at the end of January when the vessel became unmoored during the Storm Corrie and was swept towards the wind farm.

TenneT has since carried out several surveys of the damaged jacket, both above water and under water, which have shown ”…that the damage to the jacket of the platform is limited…” and that ”…the damaged parts of the jacket can be repaired at a later date.”

”The investigation now shows that the damage is limited to paint damage and some dents on one of the legs of the platform and damage to one of the four landing platforms for work ships,” TenneT said

TenneT expects the Hollandse Kust (Zuid) Beta topside to be installed at the end of March or early April.

The 700 MW topside set sail from the Drydocks World Dubai’s fabrication facility in the United Arab Emirates on 21 February.

Related Article

Hollandse Kust Zuid Beta Topside Sails Out of Dubai

The High Voltage Alternating Current (HVAC) offshore transformer station is being delivered to TenneT by Petrofac, who also delivered the Hollandse Kust Zuid Alpha substation in cooperation with Drydocks World Dubai.

Hollandse Kust Zuid Alpha has been in place at its designated location offshore the Netherlands since December 2021.

The jacket foundation for the HKZ Beta platform was installed at the site in June 2021.

The offshore platform will form part of the Hollandse Kust Zuid (HKZ) grid connection that links the offshore wind farm zone to the Dutch mainland at the Maasvlakte.

Located 20 kilometers off the Dutch province of Zuid-Holland, the wind farm zone occupies an area of 235.8 square kilometres, where Vattenfall is building four wind farms as part of the HKZ project.

Once fully operational in 2023, the 1.5 GW Hollandse Kust Zuid will become the largest operating offshore wind farm in the world. Comprising 140 Siemens Gamesa 11 MW wind turbines, the subsidy-free wind farm will generate enough electricity to meet the annual needs of more than two million households.

Follow offshoreWIND.biz on:

Related Articles

Grid Connection

Photos Reveal Damage to Offshore Substation Jacket Hit by Drifting Cargo Ship

2 min read

Reach the offshoreWIND.biz industry in one go!

offshoreWIND.biz is read by thousands of professionals every day.

Increase your visibility with banners, tell your story with a branded article, and showcase your expertise with a full-page company profile in our business directory.

CONTACT

Follow offshoreWIND.biz on:

Filed under

Grid ConnectionWind Farm Update

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Trending Now

  1. 1Cadeler Adds Wind Ace to Fleet, First Stop East Anglia Two
  2. 2Turbine Installation at Thor Offshore Wind Farm Reaches Halfway Point
  3. 3South Korean Cable Maker Takes Delivery of Its Second Cable Laying Vessel
  4. 4Aker Solutions Joins Bellrock Floating Offshore Wind Farm Team

Related articles

Principle Power Wins O&M Contract for EFGL Floating Foundations
Operations & Maintenance

Principle Power Wins O&M Contract for EFGL Floating Foundations

15 days ago

Daily offshore wind news in your mailbox

Join thousands of industry professionals who start their day with our newsletter.

Subscribe free

Related news

Principle Power Wins O&M Contract for EFGL Floating Foundations
Operations & Maintenance

Principle Power Wins O&M Contract for EFGL Floating Foundations

15 days ago