GeoSea’s multi-purpose, self-propelled jack-up vessel Apollo completed the full-height testing of its jacking system on 25 June 2018 at the Uljanik Shipyard in Pula, Croatia, rising above the city and its ancient landmarks such as the Pula Arena amphitheatre and Temple of Augustus.
Van Oord has started the next campaign to install jacket foundations at East Anglia One wind farm offshore Suffolk, UK, with twelve of the units now already in place.
Boskalis’s cable laying vessel Stemat Spirit has started loading inter-array cables for the 497MW EnBW Hohe See offshore wind farm project.
Following the announcement of new Contracts for Difference (CfDs) auctions in the UK, which will add hundreds of new offshore wind turbines, the UK Chamber of Shipping called for a more meticulous approach to planning so disruption to shipping could me minimised.
Van Oord’s freshly upgraded jack-up Aeolus is currently undergoing final preparations at the Port of Vlissingen, the Netherlands, prior to heading out to the Norther offshore wind farm to install the first monopile foundations.
The first MHI Vestas 8.3MW wind turbine has been installed on Vattenfall’s 406.7MW Horns Rev 3 wind farm in the Danish North Sea.
CSBC has commenced construction of a 140m barge that will serve the offshore wind sector in Taiwan.
Van Oord’s cable lay vessel Nexus has loaded the final set of inter-array cables for the Borkum Riffgrund 2 offshore wind farm and is currently installing them at the site in the German North Sea.
Damen Shipyards Group, Ampelmann and VEEM demonstrated the capabilities of their joint marine access solution – a Damen Fast Crew Supplier 5009 equipped with an Ampelmann L-type gangway and two VEEM VG 260SD gyro stabilisers – at the end of June on Eneco’s Princess Amalia offshore wind farm in the N
Fred. Olsen Windcarrier’s jack-up Brave Tern has left the Port of Esbjerg in Denmark loaded with the first four wind turbines to be installed on Vattenfall’s Horns Rev 3 offshore wind farm in the Danish North Sea.
Fugro has completed a geotechnical survey campaign at the 480MW Saint-Nazaire offshore wind farm in France.
Norway’s OHT has signed a contract with China Merchants Heavy Industry (CMHI) in Jiangsu, China, for the construction of a 48,000 dwt semi-submersible offshore wind farm foundation installation vessel, with options to extend the program with up to three vessels.
Swire Blue Ocean’s jack-up vessel Pacific Orca has installed the first of the total of 84 Siemens Gamesa 7MW wind turbines at the Beatrice offshore wind farm site in the Outer Moray Firth, Scotland.
BigLift’s cargo ship Happy Star brought the first eleven transition pieces for the Deutsche Bucht (DeBu) offshore wind farm to the Cuxhaven port in Germany on 14 July, after loading them three days earlier in the Port of Avilés, Asturias, Spain.