EEW and CS Wind have produced the first monopiles and transition pieces (TPs) for Vattenfall’s Nordlicht 1 offshore wind farm ahead of schedule, the developer said on 19 February. The monopiles are each up to 80.5 metres long and weigh up to 1,290 tonnes, while the transition pieces reach a height o

All monopiles have been installed at the site of the 1.2 GW Baltic Power offshore wind farm, being built by a joint venture between Orlen Group and Northland Power in the Polish sector of the Baltic Sea, 23 kilometres off the coast of the Choczewo municipality. The project comprises a total of 78 fo

The vessel Seaway Aimery is laying inter‑array cables between wind turbines and the offshore converter platform at the East Anglia Three offshore wind site in the UK. The cable-laying vessel (CLV), which started the installation work in January, is supported by Seaway Moxie and will be joined by two

DEME has awarded Hellenic Cables with a contract for the supply of inter-array cables for the 390 MW BC-Wind offshore wind project in Poland, developed by Ocean Winds. Under the contract, the Greece-based manufacturer will be responsible for the design, engineering, manufacturing, testing, and suppl

Offshore construction has begun on the Bałtyk 2 and Bałtyk 3 offshore wind projects in Poland, developed by Equinor and Polenergia, which will together have 100 wind turbines and an installed capacity of 1.4 GW. The 2026 offshore construction campaign will see the installation of 100 monopiles, tran

The US government will fight the federal court decisions to grant preliminary injunctions in cases challenging the stop-work orders for offshore wind projects under construction, issued on 22 December 2025. The injunctions allowed the construction to resume while the underlying lawsuits are underway

Korea Midland Power Company (KOMIPO) is investing KRW 96.1 billion (about EUR 56 million) in the 390 MW Shinan-Ui offshore wind project, the company said on 11 February. Financing for the offshore wind farm has been secured, and offshore construction is scheduled to begin in April, according to KOMI

The first monopile foundations for Hornsea 3 offshore wind farm have arrived at Port of Teesworks in the UK from Bilbao, Spain, where Haizea Wind Group is producing the monopiles for Ørsted’s 2.9 GW project. Six XXL monopiles, of the total 197 that Hornsea 3 will comprise, arrived in two batches, wi

Germany’s total offshore wind power generation in 2025 amounted to 26.1 TWh, of which 20.8 TWh came from the North Sea and 5.38 TWh from the Baltic Sea, according to TenneT Germany, the transmission system operator (TSO) in charge of the country’s North Sea grid. In this article: With onshore wind f

The UK Secretary of State for Energy Security and Net Zero has granted consent for the Outer Dowsing offshore wind farm, being developed by TotalEnergies, Corio Generation and affiliates, and Gulf Development. The Development Consent Order (DCO) is for a 1.5 GW project consisting of up to 100 wind t

Chantiers de l’Atlantique has completed the construction and integration of two offshore electrical substations for the 660 MW Nordseecluster A offshore wind farm, currently under construction off the German coast. Each of the topsides is approximately 40 metres long and 22 metres high, with one wei

A metocean survey campaign is set to commence this month at the North Falls offshore wind farm site in the southern North Sea, approximately 40 kilometres off the East Anglian coast. The campaign will be carried out by Partrac, which will use the vessel CT Vector to deploy the metocean equipment at

Fugro is scheduled to soon start conducting geophysical surveys at a site in the Outer Moray Firth, Scotland, where Ocean Winds plans to build its 2 GW Caledonia offshore wind farm. The work, to be carried out within the wind turbine array site, will be conducted by the vessels Fugro Pioneer and Kom

CNOOD-Wenchong Heavy Industries (CWHI) has delivered all transition pieces (TP) the Chinese company was contracted to manufacture for the Scottish Inch Cape offshore wind farm. CWHI said on 10 February that it completed the load-out and on-time departure of the final batch of TPs for Inch Cape from