MHI Vestas has installed the first V164-9.5 MW turbine on a floating platform for the Kincardine offshore wind project. The first V164-9.5 MW turbine was installed on a Principle Power WindFloat platform at the installation harbour in Rotterdam, the Netherlands. The turbine is the first of five such

The Renewables Infrastructure Group Limited (TRIG) has agreed to acquire a 14.3 per cent indirect equity interest in the 714 MW East Anglia ONE offshore wind farm from Green Investment Group (GIG). The investment has been made in a 50 per cent interest in the holding company through which GIG’s init

Denmark’s Energinet has selected NIRAS to carry out Strategic Environmental Assessment (SEA) and environmental investigations for the Hesselø offshore wind farm. The contract covers consultancy services for preparing environmental assessments, planning consents, and marine environmental baseline inv

Works on bringing the Neart na Gaoithe offshore wind turbines to spin off the Scottish coast are moving forward with export cable route boulder clearance now completed. The same operations that were being carried out at the inter-array routes are paused for the winter, while activities on getting th

EOLOS has deployed its FLS200 floating LiDAR buoy in the waters where Wales’ first floating offshore wind farm, the 96 MW Erebus, will be built. The Spanish floating LiDAR supplier secured a contract for the Erebus project this summer with Blue Gem Wind, a joint venture between Ireland-based blue ec

Haizea Wind has so far sent off 20 out of the total 32 transition piece (TP) barrels for the Taiwanese Formosa 2 offshore wind farm from Spain to Indonesia. On 28 September, the company completed the delivery of the first batch of four TPs to Saipem by shipping them to the Karimun Yard in Indonesia.

The Massachusetts Department of Public Utilities (DPU) has issued an Order approving long-term contracts of the 804 MW Mayflower Wind offshore wind farm with the Commonwealth’s Electric Distribution Companies. The project is expected to provide approximately 0.1 per cent to 1.8 per cent savings on c

Van Oord has reached a halfway point on the installation of monopiles at the Windpark Fryslân nearshore wind farm in the IJsselmeer Lake, the Netherlands. In total, the 382.7 MW Windpark Fryslân will comprise 89 Siemens Gamesa 4.3 MW wind turbines installed on monopile foundations and scheduled for

Work to install the onshore cable which will connect the 950 MW Moray East offshore wind farm to the Scottish grid has ended, Siemens Energy said. The onshore cable, which starts near Banff, Aberdeenshire, takes the power generated offshore from the three 220kV subsea cables, and transmits it to the

Red Rock Power Limited has formed a 50:50 joint venture with the Irish state-owned utility ESB to develop the Inch Cape Offshore Limited wind farm development off the east coast of Scotland. Inch Cape is set to be constructed 15 kilometres off the Angus Coast. The project recently received approval

Smulders has shipped off the first four transition pieces built for Akita-Noshiro, Japan’s first utility-scale offshore wind farm. The transition pieces are now en route from the Smulders yard in Hoboken, Belgium to Sif Group in Rotterdam, the Netherlands. Smulders is building 33 transition pieces f

Cloudberry Clean Energy AS has entered into an exclusivity agreement with Downing LLP for the construction and ownership of a 100 MW nearshore, shallow-water wind farm in Lake Vänern in southern Sweden. Back in September, Cloudberry acquired Scanvind2 AS, the holding company of the Rewind Vänern off

Rambøll has secured another contract with Energinet to carry out an export cable route survey for the Hesselø offshore wind farm in Denmark. The contract concerns the proposed export cable route with landfall in Gilleleje. Two export cable routes were initially explored, thus two tender processes we

Inter-array cable testing and termination will start at the Moray East offshore wind farm around 11 November, with the first of the two campaigns for this work scheduled to commence then. The testing and termination works will be carried out from the wind turbines and offshore substation platforms a