Over the past few weeks, Manora Logistics has been transporting upper jacket foundation sections from Spain and Belgium to Newcastle, UK. Given the facts at hand, OffshoreWIND.biz inquired about the jacket parts being for the Moray East offshore wind farm. However, Manora Logistics declined to confi

Four survey vessels are ready to commence site investigations at the Sofia offshore wind project site off the UK’s North East coast. The surveys are part of a six-month site investigation campaign for innogy’s 1.4 GW project that started in February. The multi-purpose vessel Despina and survey vesse

The first three transition pieces for the Kriegers Flak offshore wind farm have been loaded onto a barge and are ready for installation, Bladt Industries said. The remaining 69 transition pieces will follow during the year. The last transition piece is scheduled to leave Bladt’s facility in Aalborg

G-tec’s drill vessel Omalius is on its way towards Ørsted’s Hornsea Four offshore wind project in the UK to carry out geotechnical investigations. The geotechnical investigations include deep soil and high-quality rock sampling, with the main focus on chalk sampling and offshore and onshore laborato

The deadline for the close of the examination period for Vattenfall’s Norfolk Boreas offshore wind farm has been pushed back to 12 October 2020. The UK Planning Inspectorate submitted a request to extend the examination period for the Norfolk Boreas development consent order (DCO) application to the

The European Investment Bank (EIB) has approved an undisclosed sum to finance the development of the 30 MW Golfe du Lion floating wind project offshore France. The demonstration floating wind farm will feature three V164 MHI Vestas 10 MW wind turbines supported by Principle Power’s WindFloat semi-su

Oceaneering International Services Ltd (OISL) is about to start clearing the inter-array cable routes at the Moray East site. According to a Notice of Operations, boulder clearance at the export cable routes should finish on 12 May. Immediately after that, the same work at the inter-array routes is

The European Investment Bank (EIB) has approved a EUR 500 million loan to finance the development of the Hollandse Kust (noord) offshore wind project. The loan application was submitted by the Kingdom of the Netherlands. Located 18.5 kilometres off the west coast of the Netherlands, the Hollandse Ku

Van Oord’s heavy lift vessel Svanen has arrived at the Kriegers Flak offshore wind project in Denmark to begin the installation of monopile foundations. The monopiles, manufactured by EEW Special Pipe Constructions, will be transported floating from Rostock, Germany, to the project site. The transit

Jan De Nul will set up a logistics and operations hub for the 376 MW Formosa 2 offshore wind farm project in the Port of Taichung, Taiwan. Jan De Nul and a subsidiary of the Taiwan International Port Corporation (TIPC) signed a lease and operating agreement covering a total of around 15 hectares of

MOJO Maritime France SAS has won a contract to investigate potential unexploded ordnance (UXO) targets along the export cable route connecting the Saint-Nazaire offshore wind farm to the French grid. MOJO Maritime will, through the use of ROVs and/or divers, investigate and identify the nature of th

The first Ming Yang turbine has been installed at the Zhuhai Jinwan offshore wind project in China. The first of the project’s 55 MySE5.5MW turbines was installed on 6 May at the site located in the southern part of Sanzao Island, Zhuhai City. The 300 MW offshore wind farm is being developed by Guan

Enbridge is selling 49% of its 50% stake in Éolien Maritime France (EMF), the developer of three offshore wind projects in France, to the Canada Pension Plan Investment Board (CPP Investments). After the transaction closes, through its investment in EMF, Enbridge will own equity interests in the Sai

Shell and Eneco have jointly submitted a bid in a zero-subsidy round of the tender to develop the Hollandse Kust (noord) offshore wind farm in the Dutch North Sea. The two companies are, through their CrossWind joint venture, competing with several other bidders including Ørsted, to develop a wind f