Van Oord’s installation vessel Aeolus has wrapped up sea trials off the North Holland coast, marking the completion of the modification campaign that commenced in 2017. Now, the vessel is ready to start working on the Norther offshore wind farm.
Fred. Olsen Windcarrier’s jack-up Brave Tern has arrived in Esbjerg, Denmark, and is loading the first set of wind turbine components to be installed on Vattenfall’s Horns Rev 3 offshore wind farm.
Alpha Offshore Service is carrying out repair works on some 80 blades of the 44-metre Vestas V90 3MW turbines at the Offshore Windfarm Egmond aan Zee (OWEZ) in the Netherlands, after the company signed a contract with NoordzeeWind, a joint venture between Nuon (Vattenfall) and Shell.
The technical staff of Ohio Power Siting Board (OPSB) has published its Report of Investigation, recommending that the Board approves the construction of the proposed Icebreaker offshore wind farm in Lake Erie, subject to certain conditions.
The first transition piece will be installed on the Horns Rev 3 wind farm mid-July, Vattenfall, the owner and developer of the 406.7MW project in the Danish North Sea, said.
Fugro has commenced marine site characterisation work at the Hornsea Project Two offshore wind farm site under a contract with Ørsted for geotechnical site investigation, which follows earlier contracts for geophysical investigation services at the site.
Siemens will supply sulfur hexafluoride (SF6)-free, gas-insulated 8VM1 high-voltage switchgear (GIS) to Siemens Gamesa for East Anglia ONE wind turbines. The 102 units of SF6-free GIS will be delivered to the turbine manufacturer by mid-2019.
Bladt Industries has signed two contracts with Jan de Nul and Parkwind, under which the foundation manufacturer will deliver 23 monopiles and transition pieces for Northwester 2 wind turbines, and one monopile and transition piece for the project’s substation.
Green Giraffe and FIH Partners have announced the closing of the restructuring of almost EUR 1.3 billion senior facilities in place on the Veja Mate project in Germany, owned by Highland Group Holdings Ltd, Siemens Financial Services and CI II (managed by Copenhagen Infrastructure Partners).
The first of the total of 60 wind turbines has been installed at the Arkona offshore wind farm, located off the coast of Rügen in the German Baltic Sea.
CCCC Third Harbour Engineering has won contracts for two offshore wind projects in China, valued at some RMB 1.6 billion (approx. EUR 204 million) in total.
Ørsted has awarded NKT with a contract worth over EUR 145 million, under which NKT will supply more than 190 kilometres of 220kV high-voltage AC XLPE offshore export cable system for the Hornsea Project Two offshore wind farm in the UK.
The installation of the full-scale Elisa offshore wind turbine prototype at the Plocan site off Gran Canaria, Spain, has been completed and now the turbine is awaiting the connection to the grid.
Navantia has completed the construction of the East Anglia ONE offshore substation (topside), which is scheduled to set sail from the shipyard at Puerto Real in Spain in early August and arrive at the UK construction site in early September.