The installation of transition pieces is nearing completion on the Teesside offshore wind farm. The 22nd yellow coloured transition piece was recently installed with work underway on the next. The transition pieces sit on top of all the 27 foundation monopiles. Elsewhere, work has also started on th
The construction of Anholt Offshore Wind Farm is subject to much attention. In mid-September, the Danish Wind Industry Association, Vindindustrien, and DONG Energy invited around 200 guests to visit the wind farm, and on Tuesday 25 September, the French ambassador to Denmark, Véronique Bujon-Barré,
In early September the London Array Consortium started installing London Array’s last export cable. The export cables run from offshore substations to the onshore substation at Cleve Hill, where the power generated by London Array will flow into the national electricity network. The cables have been
The third round of consultation for the GBP 3 billion Navitus Bay Wind Park project has been rescheduled for February next year, as the feedback from the second round was tremendous. Delaying the consultation will allow full consideration of the response and ensure any changes to the proposals can b
The company Ailes Marines, created by IBERDROLA and EOLE-RES to develop the offshore wind farm in the bay of Saint Brieuc, announces the launch of two technical feasibility campaigns. These campaigns will be conducted on the site of the future offshore wind farm in the bay of Saint Brieuc. Ailes Mar
Deepwater Wind expects to submit applications for state and federal permits for the Block Island offshore wind farm next month. Chief administrative officer of the company, Jeffrey Grybowski is quoted on The Day news site as saying that they have completed the three-year environmental research. The
An offshore wind project, worth a total of EUR 2.6 billion, could get a EUR 500 million loan from the European Investment Bank (EIB). The developer, Typhoon Offshore BV, plans to build the 600MW offshore wind farm 85 kilometers north of the Dutch island of Schiermonnikoog. Once built, by the end of
Today His Royal Highness, Crown Prince Haakon of Norway will officially open the Sheringham Shoal offshore wind farm built off the coast of Norfolk, the UK, by the owners Statoil and Statkraft. The Crown Prince will open the wind farm at an official ceremony at historic Holkham Hall in North Norfolk
HRH Crown Prince Haakon will officially open the Sheringham Shoal offshore wind farm at a ceremony at Norfolk’s Holkham Hall on Thursday, the Foreigner news portal says. With the last wind turbine installed on July 10, the project had its ups and downs during the development. Besides the delays caus
The first CO2-free power is now being fed into the Danish power grid from Anholt offshore wind farm. The first turbine in the farm was installed on Monday 3 September and today, just under three weeks later, the first turbine has exported power into the Danish power grid. On its completion next year
The foundations for the English Lincs Offshore Wind Farm have now been handed over to the client, who has begun to install the first wind turbines. The foundations for green energy to 200,000 UK households are now in place. MT Højgaard has handed over the foundations for 75 offshore wind turbines fo
Vattenfall’s Ormonde Offshore Wind Farm, off the coast of Cumbria, UK, was officially inaugurated today. The energy company’s CEO and President, Mr Øystein Løseth, hailed an exceptional engineering achievement which shows the way forward for offshore wind power in Europe. Mr Løseth was joined by loc
The first three tripod foundations for the offshore wind farm Global Tech I have been shipped with the INNOVATION heavy-lift jack-up vessel from Bremerhaven to the construction area. This will start the construction of the wind farm, which is located 180 kilometers north-west off Bremerhaven in the
The on-schedule connection with the grid for the offshore wind park ‘Deutsche Bucht’ is now a good deal closer. At the hearing with the Federal Network Agency yesterday, it became clear in intensive negotiations over several hours that both sides – the wind park builder Windreich AG and the network