The Town and County of Nantucket in Massachusetts and GE Vernova have reached a settlement agreement worth USD 10.5 million (approximately EUR 9 million), which the wind turbine OEM will pay to compensate the Town and local businesses for losses resulting from the failure of a turbine blade on the V

Estonia’s Consumer Protection and Technical Regulatory Authority (CPTRA) has refused to initiate the superficies licence proceedings for the Saare 7 offshore wind farm area, as the auction process did not result in a winning bidder. In May, CPTRA announced an auction for the development of an offsho

RWE officially opened its ‘Grimsby Hub’ offshore wind operations and maintenance (O&M) facility in the UK on 9 July. From the new O&M base, located at Associated British Ports’ (ABP) Port of Grimsby, RWE’s teams will maintain and operate the Triton Knoll and Sofia offshore wind farms. The Grimsby Hu

Heerema Marine Contractors’ heavy-lift vessel Aegir has installed the final suction bucket jacket foundation at Ørsted’s 920 MW Greater Changhua 2b and 4 offshore wind farms in Taiwan. According to the company’s latest social media post, the crew onboard Aegir installed a total of 66 foundations at

LS Cable & System and its subsidiary LS Marine Solution have won contracts for the supply and installation of cables for the 532 MW Anma offshore wind project in South Korea. The contracts are worth KRW 255 billion (approximately USD 185 million). LS Marine Solution will be responsible for laying th

Entrion Wind’s Top Mooring Assembly (TMA) Monopile technology has completed the Technology Qualification (TQ) process and has received a formal Statement of Feasibility from DNV. The Statement of Feasibility was awarded following an evaluation under DNV-SE-0160, passing “a rigorous vetting process”

RWE and marine nature-inclusive design specialist ARC Marine have launched a pilot project to install ARC Marine’s reef cubes at the Rampion offshore wind farm in the UK. The reef cubes are designed to both protect the wind turbine foundations and enhance marine biodiversity, according to the two co

The 476 MW Baltic Eagle offshore wind farm in Germany has reached full energisation, the joint venture between Iberdrola and Masdar said on 10 July, as they announced a joint investment in the East Anglia Three offshore wind farm in the UK. Baltic Eagle comprises 50 Vestas V174-9.5 MW wind turbines

The UK government has opened a window for registrations for the Allocation Round 7 (AR7) of the country’s Contracts for Difference (CfD) scheme, ahead of the call for applications which is expected to be launched next month. The registration period is currently scheduled to close on 27 August, accor

DNV has been awarded a contract by Ventyr, a consortium consisting of Parkwind and Ingka Investments, for the Design Certification of the Sørlige Nordsjø II wind turbines and offshore substation in Norway. “Certification plays a vital role in ensuring the safety, quality, and reliability of offshore

A decree has been approved by the Italian government to establish offshore wind manufacturing and assembly hubs at the ports of Augusta and Taranto. The total investment amounts to EUR 78.3 million, to be distributed over three years starting in 2025. Funding will come from the reallocation of reven

Ørsted has secured a finance package of approximately TWD 90 billion (about EUR 2.64 billion) for the 632 MW Greater Changhua 2 offshore wind project in Taiwan. The developer reached financial close on the project finance package with 25 banks and five Export Credit Agencies (ECAs). This is part of

Spanish renewable energy developer Iberdrola and UAE clean energy company Masdar have signed an agreement to co-invest in the 1.4 GW East Anglia Three project in the UK through what the partners say is the largest offshore wind transaction of the decade. Under the agreement, after the closing of the

The UK government and Japan’s Sumitomo Corporation have signed a memorandum of understanding, under which the company plans to invest GBP 7.5 billion (approximately EUR 8.7 billion) into infrastructure and renewable energy projects across the UK by 2035. The investment will be focused on key offshor