PGE Polska Grupa Energetyczna (PGE) and Ørsted have signed a contract with Grupa Przemysłowa Baltic for the production and delivery of additional secondary steel structures for the Baltica 2 foundations that will be installed in the Polish Baltic Sea. Grupa Przemysłowa Baltic will manufacture the pl

Heavy lift vessel (HLV) Seaway Alfa Lift, which recently completed the installation of transition pieces (TPs) at Dogger Bank B, has started the same work at the Dogger Bank C offshore wind site in the UK. According to the latest Notice of Operations for Dogger Bank C from Dogger Bank Wind Farm, the

Norway’s VARD has selected Brunvoll’s extensive propulsion and manoeuvring system for a new offshore subsea construction vessel (OSCV) it is building for Taiwan-based Dong Fang Offshore (DFO). The 121.3-metre-long vessel of VARD 3 39 design is said to be a highly versatile platform designed and equi

South Korea’s Energy Agency has announced a competitive bidding for offshore wind projects with a capacity of 1.25 GW and 1 GW solar projects in the first half of 2025. The offshore wind tender for the first half of this year will focus on fixed-bottom projects. Out of the total 1.25 GW capacity, 50

Ireland’s offshore wind energy ambitions are in jeopardy unless the government takes immediate and decisive action, Wind Energy Ireland (WEI) has warned. The industry organisation issued the warning at the launch of its new Offshore Wind Action Plan on 27 May, at the start of its annual Offshore Win

Energy companies from Singapore, Malaysia, and Vietnam have signed a joint development agreement to explore cross-border renewable energy links, focusing on exporting offshore wind power from Vietnam. Through this agreement, Malaysia, as represented by MY Energy Consortium, a consortium established

A new research project – which gathers industry and academia partners from Germany, the Netherlands and Denmark – is said to enable a more accurate modelling of offshore wind energy wake effects in the North Sea. The joint research project, named EuroWindWakes, launched in late 2024 with the aim of

The second scour protection campaign at the 496 MW Dieppe Le Tréport offshore wind farm in France has been completed. The next step is the installation of the offshore substation, which is scheduled to take place in June. DEME’s Rollingstone vessel, mobilised since the beginning of March, has finali

Fugro will carry out an offshore geotechnical survey at the Morgan and Mona offshore wind sites in the UK, starting on or around 2 June. Using its geotechnical drilling vessel Fugro Synergy, the company will be drilling, sampling and coring boreholes throughout the array areas, with the works estima

ZTT’s flagship monopile installation vessel Zhongtian 39 has completed the foundation piling for China Resources Power’s Cangnan No.1 Phase II offshore wind farm expansion project. The 215-metre-long Zhongtian 39 has installed all 13 foundation piles for the 204 MW Cangnan No.1 Phase II offshore win

Holland Home of Wind Energy (HHWE) and NMT-IRO, an organisation established by the Netherlands Maritime Technology and the Association of Dutch Suppliers in the Offshore Energy Industry, will merge as of 1 January 2026. “This is a strategic alliance that unites the strongest players in the Dutch mar

Norway-based vessel operator and service provider, Integrated Wind Solutions (IWS), has reported revenue for its business unit providing offshore wind vessels, IWS Fleet, of EUR 14.2 million in the first quarter of 2025 (Q1 2025) and new contracts and contract extensions that were signed during the

The Lillebælt Syd and Jammerland Bugt offshore wind farms are moving forward as planned after the Danish Energy Complaints Board rejected complaints against their establishment permits. The German Nature and Biodiversity Conservation Union (NABU) and Red Lillebælt and Beskyt Jammerland Bugt have fil

The Romanian Ministry of Energy has launched a call for expressions of interest for a study aimed at identifying suitable areas in the Black Sea for offshore wind development, supporting the rollout of at least 3 GW of capacity by 2035. According to the Ministry of Energy, this marks the first step