G-Tec has started geophysical survey work for ELWIND, an offshore wind project that Estonia and Latvia will build together. The Belgian company’s survey vessel Karina has been investigating the seabed in the ELWIND offshore wind farm areas in Estonia and Latvia since early September, with the work e

The first of two platforms for the 976.5 MW Gennaker offshore wind farm, developed by Skyborn Renewables, has been moved out of the construction hall at the Smulders yard in Vlissingen, the Netherlands. OSS Darß, which was transported out of the construction hall in September, currently weighs 3,800

The world’s largest semi-submersible crane vessel (SSCV), Heerema Marine Contractors’ Sleipnir, is scheduled to place the offshore substation (OSS) topside on top of the jacket foundation that the vessel recently installed at the East Anglia Three offshore wind farm site in the UK. In August, Sleipn

Hellenic Cables has been awarded a contract by Seaway7 for the supply of approximately 165 kilometres of 66 kV inter-array cables and associated accessories for the East Anglia Two offshore wind farm in the UK. Hellenic Cables’ scope of work includes the engineering, design, manufacturing, testing,

The 25 MW Provence Grand Large floating offshore wind farm in France, developed by EDF, Enbridge, and CPP Investments, has been officially inaugurated. The Provence Grand Large floating wind project has been operating for many months, supplying electricity to the Provence-Alpes-Côte d’Azur region. I

RWE has entered into a seven-year power purchase agreement (PPA) with the British Co-op Group, one of the world’s largest consumer co-operatives and the UK’s fifth biggest food retailer, for electricity produced by the Gwynt y Môr offshore wind farm. Under the PPA, RWE will supply Co-op with a total

The first monopile has been installed at the Windanker offshore wind project site in the German Baltic Sea, marking the start of construction on Iberdrola’s third large-scale offshore wind project in the region, the company said via social media on 1 October. The monopiles are being installed by Van

RWE is marking ten years since the official inauguration of the Humber Gateway offshore wind farm in the UK. Located 8 kilometres off the East Yorkshire coast, the 219 MW offshore wind farm became fully operational in 2015. It was inaugurated on 30 September 2015 by Andrea Leadsom MP, who was the Mi

The County Administrative Board of Uppsala has recommended that the Swedish government grant a permit under the Act on the Swedish Exclusive Economic Zone (SEZ) for Deep Wind Offshore’s planned Olof Skötkonung offshore wind farm. “Offshore wind is the fastest tool the Government has to bring large-s

The offshore substation (OSS) for the Sunrise Wind project, a new offshore wind farm Ørsted is building in the US, has been installed and is now undergoing commissioning work. The OSS was installed by Saipem’s heavy lift installation vessel Saipem 7000 in the first half of September, according to in

Ørsted has signed a Memorandum of Understanding (MoU) with Korea South-East Power (KOEN) to explore KOEN’s potential participation in the development of Ørsted’s 1.4 GW Incheon offshore wind project in South Korea. Located approximately 70 kilometres off the coast of Incheon, the 1.4 GW project is t

More than half of the total 100 wind turbines are now in place at RWE’s Sofia offshore wind farm site in the UK. The project’s SG 14-222 DD wind turbines are being installed by Cadeler’s vessel Wind Peak, which put the first turbine in place in March. Wind Peak, operating from the port of Hull, is c

The consortium between Denmark’s Semco Maritime and Vietnam’s PTSC Mechanical & Construction (PTSC M&C) has secured an Engineering, Procurement, and Construction (EPC) contract with Synera Renewable Energy (SRE) for the offshore substation of the Formosa 4 offshore wind farm in Taiwan. Following ext

Sif has completed the manufacturing of all 52 monopile top sections for the Ecowende offshore wind farm in the Netherlands at its Roermond facility and dispatched the structures to Smulders in Hoboken, Belgium, where secondary steel will be added. Once equipped with secondary steel by Smulders, the

The first batch of monopile foundations for the 1.5 GW Baltica 2 offshore wind project in Poland has rolled off the factory floor. A total of 111 monopiles are planned to be installed at the Baltica 2 site, 107 for wind turbines and four for the offshore substation. The units are up to 100 metres [&