The consortium behind the Hibiki floating wind turbine in Japan has announced that the 3 MW two-bladed project entered commercial operation. The Hibiki barge-type floating system, the first of its kind in Japan, features the Aerodyn SCD 3 MW two-bladed turbine installed on Ideol’s Damping Pool float

The UK Secretary of State for Scotland, Ian Murray, switched on full power at the 882 MW Moray West offshore wind farm, built by Ocean Winds some 20 kilometres off the coast of Buckie. Moray West comprises 60 Siemens Gamesa SG 14-222 DD wind turbines, each of which can generate up to 14.7 MW with [&

Iberdrola has closed a strategic agreement with Japan’s Kansai Electric Power Co., Inc. (Kansai) to co-invest in the 315 MW Windanker offshore wind farm in the German Baltic Sea. After obtaining all the necessary regulatory approvals, Iberdrola will have a majority stake of 51 per cent in the assets

After installing all 95 monopiles at Dogger Bank B, the offshore installation vessel Seaway Strashnov has moved on to the third phase of the UK’s Dogger Bank Wind Farm, where it has now begun foundation work at Dogger Bank C. Seaway Strashnov and Seaway Alfa Lift commenced the installation work at D

SK oceanplant has started the production of jacket foundations that will be installed on the 495 MW Fengmiao 1 offshore wind farm in Taiwan. SK oceanplant announced today (23 April) that it held a ceremony for the offshore wind project at its yard in Goseong County, South Gyeongsang Province, South

EEW Special Pipe Constructions (EEW SPC) has delivered the first monopiles for RWE’s Thor offshore wind farm in Denmark. In March 2025, the first of twelve shipments for the 1.1 GW Thor project was completed at Rostock Port. So far, 15 out of the total 36 monopiles being produced by EEW SPC have bee

Prysmian’s new cable laying vessel (CLV) Monna Lisa has been loaded for the first time with submarine cable, destined for what will become the largest US offshore wind farm once operational. Prysmian reported two days ago that the submarine cable for Dominion Energy’s Coastal Virginia Offshore Wind

The first Siemens Gamesa 14-222 DD turbine has been installed at the Hai Long 2A offshore wind farm in Taiwan, which is being developed by a joint venture between Northland Power, Mitsui & Co., and Gentari. The Hai Long project comprises two offshore wind farms, the 518 MW Hai Long 2 and the 504 MW

The first onshore substation of the 920 MW Greater Changhua 2b and 4 offshore wind project in Taiwan has been connected to the Taiwan Power Company (Taipower) onshore substation in the Changhua Coastal Industrial Park. The energisation of the onshore substation for the Greater Changhua 2b part of th

The first onshore cables have been pulled at a site in Lower Saxony, Germany, for the BorWin4 and DolWin4 grid connection projects, marking the start of the cable laying campaigns, according to cable supplier Prysmian. The DolWin4 and BorWin4 grid connection systems, each with a capacity of 900 MW,

Following an order to halt construction activities issued by the US government, Equinor said it will suspend the offshore construction “in waters of the outer continental shelf for the Empire Wind project.” Empire Offshore Wind LLC (Empire), the project company owned by Equinor, received a notice fr

Following the order of the US Department of the Interior (DOI) to halt all construction activities on the Empire Wind 1 offshore wind project, New York Governor Kathy Hochul said she would fight the federal decision. “This fully federally permitted project has already put shovels in the ground befor

Ørsted is conducting a confirmed unexploded ordnance (cUXO) removal campaign along the export cable route of the Hornsea Three offshore wind project in the UK and a potential UXO (pUXO) inspection campaign in the array area. As of 14 April, 24 confirmed UXOs within the Hornsea Three export cable rou

The US Department of the Interior (DOI), through the Bureau of Ocean Energy Management (BOEM), has paused the building of the Empire Wind 1 offshore wind farm, which is currently under construction in federal waters off New York. According to community and mariner updates issued by the Empire Wind p