TotalEnergies and European Energy have started seabed surveys in the area surrounding the planned Jammerland Bugt offshore wind farm, located between Kerteminde on Funen and Kalundborg on Zealand, Denmark. The two companies launched three vessels to carry out seabed measurements, which will provide

Cadeler held a naming ceremony for its second P-class wind installation vessel at the COSCO shipyard in Qidong, China, on 12 March. Named Wind Pace, the jack-up is the seventh wind installation vessel in Cadeler’s fleet and will see its first deployment immediately after delivery on an offshore wind

EnBW is laying the first submarine cable of the internal wind farm cabling that connects all 64 Vestas V236-15.0 MW turbines of the 960 MW He Dreiht offshore wind farm. Seaway7 has been commissioned with the task. In 2022, EnBW awarded the company an engineering, procurement, installation, and commi

Semco Maritime and its consortium partner PTSC M&C have completed the load-out and sail-away of the second and last offshore substation for the Hai Long offshore wind project in Taiwan. “With the successful load-out and sail-away of offshore substation topsides for Hai Long 2 in April2024 and Hai Lo

Sefine Shipyard has contracted Techano Oceanlift, a subsidiary of Oslo-listed Nekkar, to deliver 150-tonne cranes for two newbuild construction support vessels (CSVs) ordered by Norwegian offshore energy vessel and service providers. One of the cranes is already in production for a CSV ordered joint

France-based Akrocean has completed the Floating LiDAR campaign for the proposed 1 GW offshore wind farm in Taranaki, New Zealand, developed by a joint venture between Copenhagen Infrastructure Partners (CIP) and NZ Super Fund. On 11 March, Akrocean announced the completion of its Floating LiDAR tur

As part of the pre-construction works at the Hornsea Four offshore wind farm site in the UK, Ørsted will carry out a geophysical survey campaign, starting in late March/early April, to investigate the physical characteristics of the seabed. The data acquired from the campaign will be used for detail

The joint venture between SSE Renewables, TotalEnergies and PTTEP has signed an agreement with a consortium of Equitix and Kyuden Group to sell the offshore transmission assets of the Seagreen Phase 1 offshore wind farm in Scotland. The Seagreen 1 transmission assets transmit electricity from the of

CSBC-DEME Wind Engineering (CDWE) has started the 2025 installation campaign for the 1 GW Hai Long offshore wind project in Taiwan. The 1,022 MW Hai Long project comprises two offshore wind farms, the 518 MW Hai Long 2 and the 504 MW Hai Long 3, and is being developed in three phases. Hai Long 2 is

The Gode Wind 3 offshore wind farm in the German North Sea is now fully commissioned, following the completion of the final testing on 28 February. The offshore wind farm, jointly owned by Ørsted and Nuveen Infrastructure, comprises 23 Siemens Gamesa 11 MW wind turbines which, with a rotor diameter

On 27 February, a turbine at the Vineyard Wind offshore wind project was struck by lightning. The GE Vernova Haliade-X 13 MW turbine had previously experienced a blade failure in July 2024. In July 2024, a blade from one of the GE Vernova’s Haliade-X turbines detached, which resulted in debris washi

Yunneng Wind Power, the joint venture that built and owns the Yunlin offshore wind farm in Taiwan, has inaugurated the 640 MW project at a ceremony held at the Santiaolun Beach & Water Park in Sihu Township. After the first turbine was connected to the Taiwanese grid in 2021, the wind farm reached i

Louis Dreyfus TravOcean and Prysmian will soon resume the inter-array cable installation at the Îles d’Yeu and Noirmoutier offshore wind farm site in France. According to a recent social media post from Louis Dreyfus TravOcean, 5 strings and 37 cables are left to be installed and connected at the si

Construction activities on the Scottish Inch Cape offshore wind farm are scheduled to start this April with construction work within the project’s export cable corridor. According to a Notice to Mariners from the project team, the work will commence with operations at the export cable landfall site