The Gippsland Dawn offshore wind project, being developed by BlueFloat Energy, has been granted Major Project Status (MPS) by the Australian Government. Gippsland Dawn is one of 16 projects nationwide to receive this recognition and the second offshore wind project being developed to hold this statu

After a delay in the construction of the onshore substation that also delayed the project’s commercial operation date, the Revolution Wind offshore wind farm in the US has faced a challenge with the installation of one of the offshore substation monopiles. This is according to the information shared

Van Oord, using its jack-up vessel Aeolus, has installed 34 of the total 100 monopiles at the Sofia offshore wind farm site in the UK, according to a Notice to Mariners issued on 29 October. Aeolus installed the first monopile at the Sofia project site, located on Dogger Bank in the central North Se

Dominion Energy has revealed that 78 monopile foundations and four pin piles for one offshore substation were installed at the 2.6 GW Coastal Virginia Offshore Wind (CVOW) project in the US during the first installation season. Dominion Energy said that it achieved its initial goal of installing at

Cadeler heavy lift vessel Wind Orca is nearing completion of turbine installations at the Moray West offshore wind farm site in Scotland, with just six turbines remaining to be installed, according to the latest Notice to Mariners. Moray West, part of Ocean Winds’ 6 GW portfolio of secured offshore

German energy company RWE has secured construction and environmental permits to build a 100 MW electrolyzer in Eemshaven, the Netherlands. The electrolyzer is part of system integration solutions associated with OranjeWind, an offshore wind project RWE is jointly developing with TotalEnergies in the

The Danish Energy Agency (DEA) has granted RWE the offshore construction permit for its Thor offshore wind farm, enabling RWE to begin construction at sea in spring 2025. RWE said that good progress is already being made on land, with the laying of cables and the construction of an onshore substatio

Several new components for the wind turbines destined for the Les Eoliennes Flottantes du Golfe du Lion (EFGL) floating offshore wind farm have arrived at the wind terminal in Port-La Nouvelle, France. The towers and nacelles for the floating wind project’s Vestas V164-10.0 MW wind turbines have bee

Global investment firm Brookfield has bought minority stakes in four UK offshore wind farms owned and operated by Ørsted for around GBP 1.75 billion (approximately EUR 2.1 billion). The buy-in, which Brookfield is pursuing through Brookfield Infrastructure Fund V, will see the investment firm acquir

The DP3 installation vessel Orion, owned and operated by the Belgian offshore construction specialist DEME, is scheduled to begin installing the remaining monopile foundations at the Vineyard Wind 1 site in the US on or around 28 October, as disclosed in the project’s recent offshore wind mariner up

Dominion Energy has completed the purchase of the Kitty Hawk North offshore wind lease area from Avangrid, Iberdrola’s US subsidiary, for approximately USD 160 million. The agreement includes a lease acquisition payment of USD 117 million, approximately USD 3,000 per acre, along with a reimbursement

The first floating solars for the Hollandse Kust Noord (HKN) offshore solar farm have arrived at the Port of Amsterdam, set for installation at the Dutch CrossWind HKN offshore wind farm. Planned for a 2025 installation, the Hollandse Kust Noord solar farm is expected to be what the company describe

Van Oord’s new, next-generation cable-laying vessel (CLV) Calypso has begun installing cables at its first offshore wind project, marking its official debut. Calypso’s first project is RWE’s Sofia offshore wind farm, being constructed on Dogger Bank in the central North Sea, 195 kilometres from the

Following a July blade failure incident, GE Vernova plans to remove some blades and strengthen others at the Vineyard Wind 1 offshore wind farm in the US. The companies are implementing the incident and response action plan, which was announced in August. The plan outlined steps to safely remove the