EEW Korea Heavy Pipe Construction (EEW KHPC) has signed a preferred supply agreement (PSA) with Anma Offshore Wind for the fabrication and supply of pin piles for the 532 MW offshore wind farm in South Korea. In this project, EEW KHPC plans to manufacture and supply 60 pin piles, a substructure that

After completing the work as the owner’s engineer delivering the front-end engineering design (FEED) for the Anma offshore wind project in South Korea, COWI has been awarded a detailed design contract for the 532 MW offshore wind farm. The Denmark-headquartered company has delivered FEED design for

Buss Energy Group (Buss) has been awarded a contract by Heerema Marine Contractors to provide marshalling services for the 960 MW He Dreiht wind farm offshore Germany. The contract is scheduled to start by the end of 2023 and will be operated by Buss Terminal Eemshaven (BTE) located in the Netherlan

As construction work continues on New York’s first offshore wind farm, James Fisher Renewables is carrying out its second contract for the project. Following the deployment of the company’s bubble curtain during foundation installation this summer, James Fisher is now engaged in the final cable work

Several days ago, Ørsted called it quits on the Ocean Wind 1 offshore wind farm in the US, with some of the main issues leading to the decision to abandon the project being supply chain bottlenecks, primarily vessel shortages. This has affected not only the now-dropped Ocean Wind 1 but also the comp

Vattenfall and TKF have signed a multi-year partnership for the supply of inter-array cables for offshore wind farms in Europe. The agreement covers the supply of 66 kV inter-array cables and will apply to all fixed-bottom European offshore wind farms developed by Vattenfall in the coming years. The

The Dutch government will open the application period for the IJmuiden Ver Alpha and Beta tender on 29 February 2024 and will accept proposals until 5 p.m. on 28 March. On 3 November, the government also informed about the additional criteria that will be part of the tender requirements. In the firs

The Connecticut Department of Energy and Environmental Protection (DEEP) has issued a Request for Proposals (RFP) for 2 GW of offshore wind generation capacity. The RFP contains a few new provisions, including an indexed pricing option that adjusts for inflation and multi-state bids under the recent

The Portuguese government launched the initial stage of the offshore wind competitive procedure on 31 October by issuing a call for expressions of interest (EoIs) that will stay open until 14 November. An expression of interest is not binding and does not constitute a precondition for proceeding wit

In an announcement on acquiring a further stake in the German Butendiek offshore wind farm earlier this month, Ireland-based Greencoat Renewables said that the project had signed one of the largest renewable energy Power Purchase Agreements (PPAs) in Germany. It has now been revealed the electricity

HBA Future Energy has been awarded a Preferred Supplier Agreement (PSA) by Anma Offshore Wind (Anma) for the provision of an offshore substation (OSS) under an engineering, procurement, construction, and installation (EPCI) contract for the 532 MW wind farm offshore South Korea. “This award reflects

The PGE and Ørsted joint venture has signed an agreement with German-based Steelwind Nordenham for the supply of foundations for Baltica 2, which is the first stage of the Baltica Offshore Wind Farm in the Polish Baltic Sea. Under the contract, Steelwind Nordenham will deliver 34 monopile foundation

Greece’s Hellenic Cables, the cable segment of Cenergy Holdings, has signed a contract with Seaway7 for the supply of inter-array cables for the East Anglia Three offshore wind farm in the UK. Under the contract, Hellenic Cables will be responsible for the engineering, manufacturing, testing, and su

3E, a Belgium-based technology and SaaS company for the wind, solar and energy storage industries, has been awarded a contract for a strike price study for the offshore wind tender(s) in the Princess Elisabeth zone. Under the contract signed on 20 October, 3E will analyse both the maximum strike pri