Siemens Gamesa has ordered 140 offshore wind turbine towers for three different projects at Denmark’s Welcon. 78 towers will be manufactured for the 1.5 GW Hollandse Kust Zuid (HKZ) wind farm in the Dutch North Sea, 38 towers for the 342 MW Kaskasi project in the German North Sea, and 24 towers for

The European Commission has approved, under EU State aid rules, Danish support for the Thor offshore wind farm project. Denmark notified the Commission of an aid measure, with a total maximum budget of DKK 6,5 billion (approximately EUR 870 million), to support the design, construction, and operatio

NKT has finalized the manufacturing and delivery of both the export cable system and the inter-array cables for the Triton Knoll offshore wind farm. The project comprises the manufacture of 100 kilometres of 220 kV HVAC offshore export cables and 144 kilometres of 66 kV inter-array cables, as well a

The Triton Knoll offshore wind project in the UK has generated its first power. According to RWE, the milestone follows the delivery of vital onshore and offshore electrical infrastructure on schedule, and despite the challenges of constructing during the Coronavirus pandemic. The project will now k

Italian oil and gas major Eni has completed the acquisition of a 20 per cent stake in the 1.2 GW Dogger Bank A and the 1.2 GW Dogger Bank B offshore wind farms in the UK. Eni bought the stakes from Equinor (10 per cent) and SSE Renewables (10 per cent). Following this transaction, the […]

The installation of Siemens Gamesa turbines at the Windpark Fryslân nearshore wind farm in the Netherlands is set to commence at the beginning of March. The 382.7 MW Windpark Fryslân will comprise 89 Siemens Gamesa 4.3 MW turbines located in the IJsselmeer Lake. According to the project developer, a

The 19 MW Borssele V wind farm in the Dutch North Sea has been fully commissioned, Two Towers, the consortium behind the ”innovation site”, said. Situated within the site III of the Borssele Wind Farm Zone, Borssele V features two Vestas 9.5 MW turbines and several innovations, one of which is a sub

The La Gan Wind Power Development Corporation has signed four Memoranda of Understanding (MoUs) covering foundation supply and harbour services for the 3.5 GW La Gan offshore wind farm in Vietnam. The MoUs were signed with Vietnam-based suppliers: CS Wind Corporation, PTSC Mechanical and Constructio

Enterprize Energy has kicked off initial marine surveys off the coast of Binh Thuan province in Vietnam for its 3.4 GW Thang Long offshore wind project. This is the largest offshore wind farm to be granted a survey licence by the Vietnamese government, the developer said. Enterprize Energy has engag

K2 Management has been appointed owner’s engineer on US Wind’s offshore wind project in Maryland. K2 Management will be supporting US Wind with project management during the development of the project’s first phase with an installed capacity of 270 MW. The scope also includes design and engineering

Rosetti Marino has cut the first steel for the jacket foundation that will support the offshore substation (OSS) at the Fécamp offshore wind farm in France. The Italian company is building the jacket at its Piomboni Yard in Ravenna for Chantiers de l’Atlantique, which won a contract for the offshore

Blue Gem Wind, the joint venture of Total and Simply Blue Energy, has submitted the scoping report for the Valorous floating offshore wind project in the Celtic Sea. The proposed Valorous site is located approximately 50 km South West of the Pembrokeshire coastline. Valorous represents the second fl

Parkwind has awarded DEME Offshore with an Engineering, Procurement, Construction and Installation (EPCI) contract for the foundations at the Arcadis Ost 1 offshore wind farm in the German Baltic Sea. The next-generation XXL monopiles will be the largest-ever installed in Europe with a weight of aro

The first transition pieces for the Saint-Nazaire offshore wind project in France have arrived at the Port of La Rochelle. Smulders shipped off the first four transition pieces for the 480 MW project in mid-February from Belgium to Rotterdam, the Netherlands, from where they were transported to Fran