The topside of the second Siemens Offshore Transformer Module (OTM2) is currently being installed on the Beatrice wind farm off Scotland, Beatrice Offshore Windfarm Ltd (BOWL) said in the latest Notice of Operations.
Vessels Edda Fonn and Voe Vanguard are on their way to the Rampion site to carry out boulder clearance and UXO identification on the CR4 export cable route, according to the project’s Notice to Mariners and vessels’ latest AIS data.
Mingyang Wind Power has installed what the company described as the world’s largest typhoon-resistant wind turbine – the MySE5.5-155 – offshore the Fujian Province in China.
Fred. Olsen Windcarrier’s jack-up vessel Bold Tern installed the first MHI Vestas 8MW wind turbine at Ørsted’s Borkum Riffgrund 2 offshore wind farm in the German North Sea on 5 May.
A2Sea’s jack-up installation vessel Sea Installer left the Port of Ostend, Belgium, on 5 May with the first 7MW Siemens Gamesa wind turbines destined for installation at the 309MW Rentel offshore wind farm in the Belgian North Sea.
Heavy lift vessel Rambiz has installed the Kriegers Flak substation topsides in the Danish Baltic Sea, Energinet reports.
The UK Secretary of State for Business, Energy and Industrial Strategy (BEIS) has approved Ørsted’s application to reduce the number of offshore substations and increase the size of the topsides on the Hornsea Project Two offshore wind project.
EDF Group has bought the Neart na Gaoithe offshore wind project from Mainstream Renewable Power, following a competitive bidding process, the two companies informed on 3 May.
The industry has been waiting for Vattenfall to give out more information on its Hollandse Kust Zuid 1 & 2 zero-subsidy bid after the company won the Dutch tender in March, especially since Ørsted – world’s leading offshore wind developer and one of the first to have unsubsidised projects in the pip
Parkwind has acquired full ownership of KNK Wind, the project company behind the 247MW Arcadis Ost 1 offshore wind farm in the Baltic Sea that won the concession rights at the latest offshore wind tender in Germany.
Fred. Olsen Windcarrier’s jack-up Bold Tern has left the Port of Esbjerg in Denmark loaded with the first set of MHI Vestas 8MW turbine components for Ørsted’s 450MW Borkum Riffgrund 2 offshore wind farm in the German North Sea.
Belgian offshore wind developer Norther NV has announced the start of offshore construction works on the 370MW Norther offshore wind farm.
Vattenfall and Peel Ports Great Yarmouth expect to finalise their agreement to locate the Swedish energy group’s offshore wind operations base at the East Anglian facility by summer 2018.
German Maritime Search and Rescue Association (DGzRS) responded to a report of a fire onboard a crew transfer vessel near the Nordergründe offshore wind farm on Monday, 30 April.