RWE has switched on what the company says is one of the largest battery energy storage systems (BESS) in the Netherlands at its Eemshaven power station. The commissioning of the ultra-fast synthetic inertia BESS at RWE’s Moerdijk power station is also underway. Both battery systems are part of the s

The first of three offshore substations has been installed at the 2.6 GW Coastal Virginia Offshore Wind (CVOW) project, located 43 kilometres off the coast of Virginia Beach, the US. The 3,907-metric tonne lift marks the completion of the installation of the first topside onto the jacket, which was

TotalEnergies and European Energy have started seabed surveys in the area surrounding the planned Jammerland Bugt offshore wind farm, located between Kerteminde on Funen and Kalundborg on Zealand, Denmark. The two companies launched three vessels to carry out seabed measurements, which will provide

EnBW is laying the first submarine cable of the internal wind farm cabling that connects all 64 Vestas V236-15.0 MW turbines of the 960 MW He Dreiht offshore wind farm. Seaway7 has been commissioned with the task. In 2022, EnBW awarded the company an engineering, procurement, installation, and commi

Semco Maritime and its consortium partner PTSC M&C have completed the load-out and sail-away of the second and last offshore substation for the Hai Long offshore wind project in Taiwan. “With the successful load-out and sail-away of offshore substation topsides for Hai Long 2 in April2024 and Hai Lo

France-based Akrocean has completed the Floating LiDAR campaign for the proposed 1 GW offshore wind farm in Taranaki, New Zealand, developed by a joint venture between Copenhagen Infrastructure Partners (CIP) and NZ Super Fund. On 11 March, Akrocean announced the completion of its Floating LiDAR tur

As part of the pre-construction works at the Hornsea Four offshore wind farm site in the UK, Ørsted will carry out a geophysical survey campaign, starting in late March/early April, to investigate the physical characteristics of the seabed. The data acquired from the campaign will be used for detail

The joint venture between SSE Renewables, TotalEnergies and PTTEP has signed an agreement with a consortium of Equitix and Kyuden Group to sell the offshore transmission assets of the Seagreen Phase 1 offshore wind farm in Scotland. The Seagreen 1 transmission assets transmit electricity from the of

CSBC-DEME Wind Engineering (CDWE) has started the 2025 installation campaign for the 1 GW Hai Long offshore wind project in Taiwan. The 1,022 MW Hai Long project comprises two offshore wind farms, the 518 MW Hai Long 2 and the 504 MW Hai Long 3, and is being developed in three phases. Hai Long 2 is

The Gode Wind 3 offshore wind farm in the German North Sea is now fully commissioned, following the completion of the final testing on 28 February. The offshore wind farm, jointly owned by Ørsted and Nuveen Infrastructure, comprises 23 Siemens Gamesa 11 MW wind turbines which, with a rotor diameter

Vattenfall has contracted DEME Offshore for cable protection system (CPS) stabilisation work on the DanTysk and Sandbank offshore wind farms in Germany. The offshore wind farm owner/operator opened the tender for CPS stabilisation work in June last year. According to a contract award notice publishe

On 27 February, a turbine at the Vineyard Wind offshore wind project was struck by lightning. The GE Vernova Haliade-X 13 MW turbine had previously experienced a blade failure in July 2024. In July 2024, a blade from one of the GE Vernova’s Haliade-X turbines detached, which resulted in debris washi

Yunneng Wind Power, the joint venture that built and owns the Yunlin offshore wind farm in Taiwan, has inaugurated the 640 MW project at a ceremony held at the Santiaolun Beach & Water Park in Sihu Township. After the first turbine was connected to the Taiwanese grid in 2021, the wind farm reached i

Louis Dreyfus TravOcean and Prysmian will soon resume the inter-array cable installation at the Îles d’Yeu and Noirmoutier offshore wind farm site in France. According to a recent social media post from Louis Dreyfus TravOcean, 5 strings and 37 cables are left to be installed and connected at the si