The first of a total of 30 wind turbines for EWE’s Riffgat offshore wind farm at the North Sea has been installed. “Further seven turbines are already on board the specialized vessel, so that Riffgat will now continue to grow very rapidly,” says EWE’s Dr. Torsten Köhne. The plan is to have the wind
Even though the wind turbine installation is expected to be completed in May, the activities in terms of wind turbine commissioning and wind farm completion will still be hectic during the summer. Small service vessels will transport the numerous technicians inside the wind farm for them to complete
At the end of April, 59 wind turbines had been connected to the grid. It corresponds to a total capacity of 212.4MW, and the capacity in Anholt Offshore Wind Farm thus exceeds the capacity of Horns Rev 2 of 209MW. This makes Anholt Offshore Wind Farm the largest offshore wind farm in Denmark. Also,
More favourable weather conditions and less waves have really jump-started the wind turbine installation in Anholt Offshore Wind Farm. At the end of April, a total of 97 wind turbines had been installed in the wind farm. Now, only 14 wind turbines need to be installed before all 111 wind turbines ha
Seacat Services, a leading offshore wind farm vessel transfer operator, has won several significant charter contracts for work taking place off the UK and German coasts. The contracts incorporate five separate offshore wind farm projects. During 2013 this will include; the 288MW Meerwind project, lo
The North East’s first large scale offshore wind farm has now started to produce electricity as work continues towards completion of the project. The first three wind turbine generators at the EDF Energy Renewables Teesside offshore wind farm have now been fully commissioned and are supplying electr
Zaratan: 3 Monopiles in 36 Hours (Germany) Following the news that almost 60 monopiles had been completed on 18 March, specialised jack-up vessel Seajacks Zaratan continues installation at a rapid pace at the Meerwind Offshore Park, installing 3 monopiles in just under 1 and a half days. VIDEO: Zara
In the night from Tuesday to Wednesday, about ten months after the start of construction, the heavy load vessel Stanislav Yudin transported the last of the 40 tripods to the construction site of Trianel’s Borkum Offshore Wind Farm and anchored it in a water depth of approximately 30 meters in the Ge
The work for the network connection of the second German offshore wind farm in the Baltic Sea, the EnBW Baltic 2, is in progress. The vessel Aura rinsed the first submarine cable section into the Baltic ground, on Saturday, 20 April 2013, for the connection of Baltic 2. A total of sixty kilometers o
At 22:00 on Sunday 21st April, Seajacks Zaratan completed hammering of the 80th and final monopile at the Meerwind Offshore Wind Park in Germany. Blair Ainslie, CEO for Seajacks said: “The installation of the final monopile yesterday at Meerwind is a significant achievement for all who have been inv
Following the news that almost 60 monopiles had been completed on 18 March, specialised jack-up vessel Seajacks Zaratan continues installation at a rapid pace at the Meerwind Offshore Park, installing 3 monopiles in just under 1 and a half days. Zaratan collected the three 675t steel structures from
The installation work for the internal transformer platform for Trianel’s Borkum wind farm was successfully completed yesterday. During a two-day mission at the construction site, 45 kilometers off the Borkum’s coast, the heavy lift vessel Oleg Strashnov lifted the 2,400-ton deck onto the substructu
Construction work at Anholt Offshore Wind Farm creates a ripple effect among the project suppliers – nationally as well as locally. The Danish wind industry has left a distinct imprint on Denmark’s largest offshore wind farm near Anholt in the Kattegat, where Danish companies account for two thirds
Forewind’s second and final stage of consultation for Dogger Bank Creyke Beck begins on Friday, April 19 with the publication of documents, plans and maps about the proposed development, including the draft Environmental Statement and Non-technical Summary. The consultation will run until Tuesday, 1