E.ON released financial result for 2011. “Despite a difficult business environment, we have made very good progress in implementing our strategy and reorganizing our company. We moved resolutely forward on our consolidation course; the worst adverse effects are behind us. E.ON 2.0, our efficiency-en
As work progresses on the installation of the new Teesside Offshore Windfarm, special measures are being taken to ensure the protection of marine mammals and other wildlife. The wind farm being established by EDF Energy Renewables is located 1.5km off the north east coast at South Gare, Redcar. Work
Germanischer Lloyd (GL) announces the release of the first comprehensive set of classification rules for Crew Boats and Offshore Wind Farm Service Craft. As the energy industry expands and installations are pushed ever further offshore and into more challenging environments, the vessels servicing th
The company will be exhibiting at Seawork at stand B-201 on May 22 – May 24. French Builder NAVALU, located on the French Atlantic Coast, in the Vendée region have just taken the first delivery of the aluminium for the structure for the NxS 24 our WFSV. The performance numbers for the vessel are bet
“Global Renewable Power Investment Outlook for 2012 – Key Factors Influencing Investment Decisions” is the latest report from GlobalData, the industry analysis specialists that offer comprehensive information and understanding of the renewable power investments. The research provides an understandin
As reported on WirralGlobe, Dong Energy’s proposed Burbo Bank Offshore Windfarm Extension would make a long ‘fence’ comprising of huge turbines around the north Wirral coast, and thus ruin Wirral’s landscape. Due to existence of certain objections to foreign company making significant profit by “vis
Anholt Wind, which is the first of three identical service vessels, that are to ensure the transport of technicians to Anholt Offshore Wind Farm, was supplied from Hvide Sande Bådebyggeri at the end of 2012. The second service vessel will be delivered in May 2012 and the third vessel in June 2013. T
Construction starts on the SylWin alpha offshore transformer platform at Nordic Yards, manufacturer of innovative special ships and major maritime projects for the offshore wind and other industries. The first steel blank cut was made in the presence of representatives of the client, Siemens Energy,
With more than 20 years experience in the wind power industry, Dong Energy is one of the leading offshore wind farm developers in the country and Gardline, with its fleet of specialist turbine transfer vessels will be transporting personnel to and from offshore wind turbines, offshore sub-stations a
Oil States Industries, Inc. announced, after two years of engineering and manufacturing work, has launched the addition of a new high-capacity NautilusR marine crane to its portfolio. The NautilusR 7000L was manufactured as part of a four-crane package mounted aboard MONTCO Offshore’s 335ft-class Li
In a letter addressed to First Minister Alex Salmond, Donald Trump said that international investors no longer see Scotland as a safe place to invest and that 83 percent of Scots consider wind farms as a “blot” on the landscape, reported Bloomberg. Trump said that Salmond is destroying Scotland’s in
At Easter, Energinet.dk’s approximately 1600 tonnes heavy top section for the offshore substation was hoisted into position with assistance from a Dutch crane vessel. The substation platform will connect the 111 wind turbines in the Anholt Offshore Wind Farm to the Danish power grid. On Good Friday
BMT Nigel Gee, a subsidiary of BMT Group, will showcase its broad portfolio of vessel designs at this year’s Seawork International which takes place from the 22nd – 24th May in Southampton. This will be BMT’s 6th year of exhibiting at this prestigious show which will see the organisation’s innovativ
On arrival at Aalborg, the vessel Jumbo Javelin started loading transition pieces at Bladt Industries on 13 April 2012, and already on 16 April the first transition piece was placed on the monopile in the wind farm. The transition piece is cast onto the monopile by means of special concrete. The tra