Jan De Nul has pulled two export cables for the 1,080 MW Thor offshore wind farm, currently under construction in Denmark. The export cables will transport clean, renewable electricity from the offshore site 22 kilometres out in the North Sea to the Danish mainland. In 2023, Jan De Nul, together wit

The final inter-array cable was installed at the 488 MW Îles d’Yeu and Noirmoutier (EMYN) offshore wind farm in France, developed by Les Éoliennes en Mer Services. The 61st and final inter-array cable was installed at the EMYN site located 11.7 kilometres from the island of Yeu and 16.5 kilometres f