The heavy-lift jack-up vessels Pacific Osprey and Innovation have transported and installed the offshore substation topside on the EnBW Albatros offshore wind farm in the German North Sea. Pacific Osprey had loaded the topside in Rotterdam. In the construction area, the Innovation lifted the topside
The jacket foundation for the Deutsche Bucht offshore substation has arrived at the installation site in the German North Sea and will be installed as soon as there is a suitable weather window, a spokesperson for Northland Deutsche Bucht GmbH told Offshore WIND. The substation topside has been towe
Transmission system operator TenneT has awarded Jan De Nul with a framework agreement for repairs of TenneT’s offshore high-voltage cables in the German Bight. Under the terms of the agreement, Jan De Nul will mobilize in the event of high-voltage cable system faults or failures within the contractu
The topside for the Deutsche Bucht substation was shipped out from the Damen Shiprepair yard in Vlissingen, the Netherlands, to the installation site in the German North Sea on 19 March. The 269MW Deutsche Bucht offshore wind farm will comprise of 33 MHI Vestas 8.4MW wind turbines installed on 31 mo
The first onshore electrical cables destined for the Triton Knoll offshore wind farm have rolled out from production and are heading towards the Port of Boston, the UK. The High Voltage Alternating Current (HVAC) cables will make up the onshore cable network, connecting power from the 860MW offshore
Global Offshore, part of Global Marine Group, has won an inter-array cable installation contract by Vattenfall for the Kriegers Flak offshore wind farm in Denmark. Global Offshore will carry out the inter-array cable installation, burial, testing and termination at the 605MW project. The company sai
Prysmian Group has won a contract to develop a turnkey cable system for the Provence Grand Large floating offshore wind project in France. Under the EUR 30 million deal, Prysmian will supply 3km of inter-array cables, 19km of export cables and onshore cables for a 9km route. All submarine cables wil
JDR Cables has secured an inter-array cable contract by Vattenfall for the Kriegers Flak offshore wind farm in Denmark. Under the deal, JDR will manufacture more than 170km of aluminium core inter-array cables and a range of termination accessories. According to the UK-based company, the cable will
Anbaric has filed a request with ISO-New England for a 1,200MW HVDC interconnection to a substation in Brayton Point, Massachusetts, that would collect energy produced by offshore wind projects. According to Anbaric, the proposal will offer expanded wind generation procurements off Massachusetts res
MFW Bałtyk III Sp. z o.o., a joint venture between Equinor and Polenergia S.A., has secured an environmental decision for the offshore grid infrastructure connecting two offshore wind farms with a total capacity of 1440MW to the Polish national grid system. The decision was issued by the Regional Di
Ofgem has appointed Diamond Transmission Partners as the preferred bidder to own and operate the offshore transmission link of the Walney Extension offshore wind farm in the UK. The consortium of HICL Infrastructure Company, Diamond Transmission Corporation and Chubu Electric Power will be operating
TenneT and the Dutch Ministry of Economic Affairs and Climate Policy (EZK) are inviting the public to provide comments on the infrastructure for connecting the North of the Wadden Sea Islands offshore wind project to the grid. The parties said that by gathering feedback on the 700MW Ten Noorden van
The key works to connect the onshore and offshore electrical circuits of the Triton Knoll offshore wind project are set to start at the end of March, according to the project developer. The activities will take place at the project’s landfall location north of Anderby Creek, the UK, and will include
Dutch transmission system operator TenneT has selected Arcadis and Pondera to carry out an Environmental Impact Assessment (EIA) and provide permit applications with associated investigations for high-voltage connections which will link the IJmuiden Ver wind farm to the grid. The two subsea high-vol