GeoSea’s installation vessel Innovation has transported the first set of monopiles for Vattenfall’s 406MW Horns Rev 3 offshore wind farm from the Port of Esbjerg in Denmark.
The first four out of the total of 49 monopiles have been installed at the Horns Rev 3 offshore wind farm site in Denmark and GeoSea’s installation vessel Innovation is now set to install the next batch.
GustoMSC has revealed a new Jones Act-compliant jack-up vessel design for the installation of wind turbines and foundations in the U.S. The SEA-3250-LT installation jack-up is capable of handling the latest generation of 8 to 9.5 MW turbines and foundations.
Landfall Marine Contractors has posted a photo of their Neptune Mariner during the delivery of one of the monopiles for the 385MW Arkona offshore wind farm in the German Baltic Sea, where they are being installed by Van Oord’s heavy lift installation vessel Svanen.
Seazip Offshore Service has posted a photo taken from its service vessel Seazip 3, showing commissioning works at the 336MW Galloper offshore wind farm off the coast of Suffolk.
Bakker Sliedrecht will deliver the main electrical power package for the offshore wind installation vessel Orion, scheduled to be delivered to its owner GeoSea in 2019. The vessel will be deployed on next-generation projects featuring massive components.
Fred. Olsen Windcarrier’s fleet of seven Bayard class crew transfer vessels (CTVs) reached 1,000 days without a lost time incident (LTI) on 12 October.
Global Marine Group is set to acquire Fugro’s trenching and cable laying business after the two companies signed an agreement under which Fugro will, in return, get an equity stake of 23.6% in Global Marine Holdings.
Havyard Power & Systems will deliver an electrical design and equipment package for Esvagt’s Service Operations Vessel (SOV) of the Havyard 831 SOV design, which will be deployed on German Deutsche Bucht offshore wind farm.
Seaway Heavy Lifting’s vessel Oleg Strashnov is currently at the Merkur offshore wind farm site as the vessel is deployed on installing the jacket foundation for the Merkur offshore substation. According to vessel’s AIS data, Oleg Strahnov has arrived at the site on 8 October.
Windcat Workboats have signed a long-term contract with CrewVessel.com, who will supply a business process and information management system to the crew transfer vessel operator.
Swire Blue Ocean’s wind turbine installation vessel (WTIV) Pacific Orca has installed 28 out of 56 turbines at the 336MW Galloper offshore wind farm, innogy reported via social media.
VBMS has awarded Vroon’s subsea-support walk-to-work vessel VOS Stone a contract to support inter-array cabling operations at the 385MW Arkona offshore wind farm from spring 2018.
Dutch engineering and consultancy company, Enersea, has reported that its engineering team is rendering fabrication support during the manufacturing of the cable lay street for Tideway’s new multipurpose vessel Living Stone.