China’s TSP Blue Island has sent off the first batch of monopile foundations for the 310 MW Binh Dai offshore wind project in Vietnam. At the end of September, 31 monopiles began their journey from Nantong, Jiangsu Province, to the Vietnamese province Binh Tre. Binh Dai will comprise a total of 74 t

Tekmar Energy has won a contract to supply its TekLink cable protection systems (CPS) for an undisclosed offshore wind farm in Germany. The UK-based cable protection specialist will supply the CPS ”for a remedial campaign on a major offshore wind farm located in the Sylt Offshore Cluster of the Germ

RWE has launched an online virtual public exhibition platform to provide residents of Dublin and Wicklow in Ireland with the opportunity to find out about the proposed Dublin Array offshore wind farm. Plans and photomontages of the wind farm are available on the project’s website. Dublin Array offsh

WSP USA will carry out a re-design of the wind turbine foundations for the Vineyard Wind offshore wind farm in Massachusetts. Following recent permitting changes, Vineyard Wind modified the turbine layout and the U.S.-based engineering consultancy will now work on the re-design, after having provide

The first turbine components for the Triton Knoll wind farm are expected to arrive at MHI Vestas’ logistics and pre-assembly hub in the Able Seaton Port in Hartlepool next month. MHI Vestas has now moved in to Able Seaton Port in preparation to start installing 90 of its V164-9.5 MW turbines at the

Smulders has sent off the final three upper jackets for the Moray East offshore wind farm from its yard in Hoboken, Belgium, to Newcastle upon Tyne. Smulders will deliver 55 turbine jacket foundations for the project, with the remaining 45 being delivered by Lamprell from its yards in the United Ara

The next phase of the onshore cable works for the Seagreen offshore wind farm in Scotland is set to start at Carnoustie Golf Links in the coming days, according to Angus Council. In August, the Seagreen team begun preparatory works for the onshore cabling project with early compound set up works at

Construction has started on the operations and maintenance, and the construction base for the 480 MW Saint-Nazaire offshore wind farm in France. The O&M base is located in the Port of La Turballe. The maintenance of the 80-turbine wind farm, scheduled to be operational by 2022, is expected to create

Qair, formerly known as Quadran Énergies Marines, has signed a preferred supplier agreement with MHI Vestas for three 10 MW offshore wind turbines for the EolMed floating wind pilot project in France. This will be the second floating wind project in which the company’s V164 turbine’s nominal capacit

National Grid and Ørsted have begun mobilizing teams that will work on replacing limited segments of the Block Island wind farm and sea2shore transmission cables to achieve greater burial depths. Construction-related activities will be ongoing throughout the fall and winter, with an anticipated comp

The jacket foundation for the offshore substation at the Hornsea Two offshore wind project in the UK has been installed. The installation of the 4,800-tonne jacket marks the start of the project’s offshore construction. Six weeks ago, 10,000 tonnes of steel framework for the pin piles, reactor compe

The Spanish Navantia-Windar consortium has launched the production of foundation components for the Saint-Brieuc offshore wind farm in the Brest polder, France. Navantia-Windar has presented the main achievements delivered in its construction program for 34 of the 62 foundations that will be built i

Danish transmission system operator Energinet is starting offshore surveys at the Hesselø wind project offshore Denmark. Fugro is deploying two vessels to carry out a geophysical survey of the 248 km2 area located in Kattegatt, 20-30 kilometres north of Sjælland. The campaign is expected to be condu

Cable laying vessel Living Stone has started the first inter-array cable installation campaign at the 950 MW Moray East wind farm offshore Scotland. The wind farm will feature 100 66 kV inter-array cables and two offshore substation interconnector cables supplied by JDR Cable System. The installatio