Vryhof has selected FMGC (Fonderie et Mécanique Générale Castelbriantaise) to provide its clump weights for the 25MW WindFloat Atlantic floating wind project offshore Portugal. WindFloat Atlantic, owned by Windplus SA, is expected to be fully operational in the second half of 2019 some 20 kilometers
The Estonian government will not issue a building permit to the developer of a 600MW offshore wind farm in the Estonian Baltic Sea, citing national security concerns as the reason for the decision. The 600MW Saaremaa offshore wind farm is being developed by Saare Wind Energy OU. The company proposes
The UK Planning Inspectorate has completed the examination of the environmental impact assessment (EIA) of Ørsted’s Hornsea Project Three offshore wind farm. The Examining Authority will now compile a report comprising conclusions and recommendations in respect of the application. The report is then
Windhoist Limited has pre-assembled the 84th and final wind turbine tower on the Beatrice Pre-Assembly Project at Nigg Energy Park in Scotland. Siemens Gamesa awarded Windhoist with a contract to carry out wind turbine pre-assembly work for the 588MW Beatrice wind farm in May 2018, marking the Scott
All 20 foundation monopiles built for the Formosa 1 Phase 2 have left the EEW SPC yard in Germany onboard two heavy load transport vessels and are en route to Taichung port in Taiwan, Jan De Nul said. Now that these components for the offshore construction are mobilized, the actual installation oper
Fred. Olsen Windcarrier’s jack-up vessel Brave Tern has installed the first turbine at the 497MW EnBW Hohe See offshore wind farm in Germany. According to EnBW, the first Siemens Gamesa 7MW turbine was put in place on Friday, 5 April, at the offshore site some 95km north of Borkum and 100km northwes
Vineyard Wind will implement recommendations from the University of Massachusetts Dartmouth’s School for Marine Science and Technology (SMAST) to guide the fisheries monitoring studies during the construction of the 800MW wind farm offshore Massachusetts. The recommendations will also be used to ini
Jack-up vessel Pacific Orca is installing the 70th Siemens Gamesa 7MW wind turbine on the 588MW Beatrice wind farm in the Outer Moray Firth, Scotland, Beatrice Offshore Windfarm Limited (BOWL) said. In total, Beatrice will comprise 84 wind turbines once fully built. The wind turbines are being commi
Fred. Olsen Windcarrier’s jack-up vessel Brave Tern has departed the Port of Esbjerg carrying the first turbines destined for the EnBW Hohe See offshore wind farm in Germany. According to the Danish port, the 132m long vessel sailed out yesterday morning with the first batch of Siemens Gamesa 7MW tu
German offshore wind developer wpd has signed a share purchase agreement with Starwind Offshore GmbH to sell a 27% stake in the 640MW Yunlin offshore wind project in Taiwan. Starwind Offshore GmbH is a German holding company established jointly between the Japanese companies Sojitz; JXTG Nippon Oil
Heavy lift vessel Seaway Strashnov has installed the jacket foundation and the substation topside on the 269MW Deutsche Bucht offshore wind farm in the German North Sea. “With the installation of the offshore substation completed, we have once more accomplished another milestone on schedule,” said J
Pondera Consult has won a contract to carry out an Environmental Impact Assessment (EIA) for lots VI and VII in the Hollandse Kust (west) offshore wind energy area in the Dutch North Sea. Pondera will manage the environmental impact assessment, the appropriate assessment, and the assessment for the
Teesside-based EEW Offshore Structures Britain has rolled out the first of the 35 transition pieces (TPs) built for Ørsted’s Borssele 1 + 2 offshore wind farm in the Dutch North Sea. The first TP was photographed on its way to the blast shed, EEW OSB said. EEW SPC, the parent company of EEW OSB, is
Grimsby’s Royal Dock has been confirmed as the home for Triton Knoll’s offshore construction and operations and maintenance facility after the project signed a port lease with ABP in Grimsby. A new construction and longer-term Operations and Maintenance base will be constructed across nearly four ac