Fred. Olsen Windcarrier’s jack-up vessel Bold Tern has installed the first MHI Vestas 8MW turbine on a suction bucket jacket foundation at the Borkum Riffgrund 2 offshore wind farm.
Turbine installation team working on the Merkur offshore wind farm has reached a halfway point on this 396MW project in the German North Sea.
The UK Planning Inspectorate has accepted for examination Ørsted’s application for the Hornsea Project Three Development Consent Order (DCO).
Fred. Olsen Windcarrier’s jack-up Bold Tern is completing its fifth run on Ørsted ‘s Borkum Riffgrund 2 offshore wind farm and is currently installing the 19th MHI Vestas 8MW turbine at the site in the German North Sea.
Horizon Geosciences and subcontractor Seaforth Geosurveys have completed the fieldwork phase for geophysical surveys and geotechnical investigations at the Vineyard Wind offshore wind project in Massachusetts, US.
Formosa 1, Taiwan’s first offshore wind farm, has reached financial close.
Danish offshore foundations specialist Bladt Industries has shipped out the final jacket foundation built for the Beatrice offshore wind project in the Scottish North Sea.
Heerema’s vessel Thialf has installed the jacket foundation for the EnBW Hohe See offshore substation (OSS) at the project site in the German North Sea.
Human remains dating back to the 11th century were found during excavation work on the South Downs for the Rampion offshore wind farm, with the body showing signs of a traumatic death, E.ON said. Archaeologists from Archaeology South East, UCL, working on behalf of the Rampion project, uncovered the
Jiangsu Hengtong High Voltage Submarine Cable, a subsidiary of Hengtong-Optic Electric, has won a contract to provide 220kV submarine power cables for the Yangjiang Nanpeng Island wind farm offshore Guangdong province, China.
Triton Knoll Offshore Windfarm Ltd has applied to the UK’s Marine Management Organisation for a marine licence to undertake boulder clearance and seabed preparation works within the Triton Knoll offshore wind farm array zone.
Japan’s Mitsui & Co has acquired a 50% stake in Yushan Energy Company Ltd which owns a 40% interest in the Hai Long offshore wind development in the Taiwan Strait between Taiwan and mainland China.
GeoSea’s jack-up vessel Innovation has installed the first out of a total of 20 suction bucket jacket foundations at Ørsted’s Borkum Riffgrund 2 offshore wind farm in the German North Sea.
The Merkur offshore wind farm has produced its first power following a successful test on one of the wind farm’s GE Haliade 6MW wind turbines, according to Merkur Offshore GmbH.