The Netherlands Enterprise Agency (RVO.nl), part of the Dutch Ministry of Economic Affairs, issued a call for tenders for geophysical soil investigations at the Hollandse Kust Noord offshore wind farm zone on 5 April.
Seaway Heavy Lifting (SHL) installed the first cluster of foundation piles at the Beatrice offshore wind farm site on 2 April, according to the Beatrice Offshore Wind Limited’s (BOWL) social media pages.
Following the start of construction at the Beatrice offshore wind farm site in the UK, Smulders posted photographs of the upper parts of the jacket foundations the company has been fabricating for the project.
Jan De Nul’s heavy-lift jack up vessel Vole au vent will now be mobilised for work on the Tahkoluoto offshore wind farm in Finland, after completing turbine installation at the Nobelwind wind farm off the coast of Belgium.
Triton Knoll Offshore Wind Farm, a project company comprising innogy and Statkraft, has awarded Dalcour Maclaren with a contract for Land Agent services as preparation for the onshore construction are under way.
The topside for the Rampion offshore substation has departed Rosyth and is on its way to the project site.
The last turbine at Belgian Nobelwind offshore wind farm was installed at 8:50am on 3 April, according to MHI Vestas Offshore Wind’s social media pages.
After fulfilling one of the prerequisites for the sale of its 40% share in the Sheringham Shoal offshore wind farm by transferring the operator role to Statoil, Statkraft will commence the formal divestment process in June, together with that for its 30% share in the Dudgeon offshore wind farm.
Norwegian energy company Statoil will take over the operatorship of the 317MW Sheringham Shoal offshore wind farm from compatriot Statkraft on Saturday, 1 April.
On 28 March, the UK Planning Inspectorate issued a report of recommendation on the East Anglia THREE offshore wind farm to the Secretary of State for Business, Energy and Industrial Strategy (BEIS), Greg Clark, who now has three months to issue a decision.
The 332MW Nordsee One offshore wind farm has started delivering power to the German grid, Nordsee One GmbH, the owner and developer of the project, reports.
The second offshore substation built by the Engie Fabricom/Iemants consortium for DONG Energy’s 660MW Walney Extension wind farm has set sail from the Engie Fabricom site in Hoboken, Belgium, bound for the wind farm in the Irish Sea.
MHI Vestas Offshore Wind has signed a conditional agreement for the Borssele III & IV offshore projects in the Netherlands, for which the consortium comprising Shell, Eneco, Van Oord, and Mitsubishi/DGE won the tender in December 2016.