TGS is scheduled to start geophysical survey work across the Dogger Bank South (DBS) offshore wind farm sites in the UK on 27 March. According to a Notice to Mariners issued by the DBS project, the Norway-based energy data and intelligence company will be using the seismic vessel Ramform Vanguard, s

Vattenfall has made the final investment decision on the Nordlicht 1 and 2 offshore wind farms in the German North Sea, with the construction scheduled to begin in 2026. In addition, the Swedish utility has decided to repurchase the shares in the Nordlicht cluster that BASF acquired in 2024. The fin

Vena Energy has decided to invest in a 384 MW offshore wind project located in South Korea’s South Gyeongsang Province. The investment includes USD 200 million (approximately EUR 184 million) for the Yokji offshore wind farm, which is being developed 10 kilometres to the west of Yokji island and 10

The 1.2 GW Baltic Power offshore wind project, a joint venture between Orlen and Northland Power, has obtained the first design conformity certificates for its turbines and offshore substations, issued by DNV. The certificates, issued by DNV, verify that the construction designs of the wind turbines

The offshore substation (OSS) of the Greater Changhua 2b and 4 offshore wind project has been installed at its designated location 47 kilometres off the southwest coast of Taiwan. The OSS components were transported to the site by Boskalis’s vessels Mighty Servant 3 and Transshelf, and the installat

On 19 March, Shinfox Far East Energy announced that the company installed the first jacket foundation at the 300 MW Taipower Offshore Wind Project Phase II (TPC Changhua Phase II) in Taiwan. The jacket, taller than a 20-storey building and heavier than 10 Boeing 747s, will provide solid support for

Cadeler’s wind turbine installation vessel (WTIV) Wind Peak is en route to the site of the Sofia offshore wind farm with the first set of Siemens Gamesa’s SG 14-222 DD turbine components. The vessel departed the port of Hull on 20 March, according to the available AIS data, and is heading towards th

Hellenic Cables, in a consortium with Asso.subsea, has been awarded a turnkey contract by the French transmission system operator (TSO) Réseau de Transport d’Électricité (RTE) for the Dunkirk offshore wind farm. Hellenic Cables will design, manufacture, and supply 32 kilometres of submarine cables f

Seabed preparation activities are scheduled to begin at the Inch Cape offshore wind farm site in Scotland at the end of March. N-Sea, which has been contracted for the job, will start the work within the array site and the export cable corridor on or around 30 March and continue until November 2025.

According to new research conducted by the Netherlands Organisation for Applied Scientific Research (TNO) in collaboration with offshore wind farm operators such as Eneco, Shell, and Equinor, a substantial part of the damage that wind turbine blades suffer per year occurs across twelve hours of hars

Ignitis Group, whose company Ignitis Renewables is developing Lithuania’s first offshore wind farm, says the commercial operation date (COD) for the 700 MW project could be postponed as large-scale electrolysis projects across Europe face delays, reducing power offtake visibility. The company, in a

Copenhagen Infrastructure Partners (CIP), through its fund Copenhagen Infrastructure V (CI V), has reached financial close on the 495 MW Fengmiao 1 offshore wind project in Taiwan, which will feature Vestas 15 MW turbines. Fengmiao 1 has secured approximately TWD 103 billion (about USD 3.1 billion)

Denmark’s Copenhagen Infrastructure Partners (CIP) has signed a Power Purchase Agreement (PPA) with MediaTek, a Taiwanese semiconductor company, for the Fengmiao 1 offshore wind farm. Under the agreement, MediaTek will purchase power from the 500 MW Fengmiao 1 offshore wind farm, being developed by

UK-headquartered Enshore Subsea has secured an export cable installation contract for one of Scotland’s largest offshore wind projects, the 1.1 GW Inch Cape. The Inch Cape offshore wind farm will feature two 85-kilometre, 220 kV, three-phase export cables, each delivered in three sections and requir