NKT has secured a cable service contract with Irish power grid operator EirGrid for the East West Interconnector between Ireland and Great Britain. Under the five-year service agreement, NKT will carry out repair works for the 200kV HVDC power cable with a capacity of 500MW. The deal includes inspec

Wind farms operating offshore Germany generated 24.16 terawatt-hours (TWh) of electricity in 2019, an increase of 26.5% compared to 19.1TWh of electricity generated offshore in 2018. Wind farms in the North Sea generated 20.21TWh of electricity in 2019, a 20.7% increase compared to 2018 when 16.75TW

The consortium has also cut the first steel for the electrical substation for the Saint-Nazaire offshore wind farm at Chantiers de l’Atlantique shipyard in Saint-Nazaire.

China’s Dongfang Electric Corporation (DEC) has awarded Prysmian Group with a contract to supply cables for DEC’s 10MW offshore wind turbine prototype. The prototype turbine will be installed on China Three Gorges Corporation’s Xinghuawan wind farm in the Fujian province, China. The nacelle of the p

TenneT has awarded RPS Energy Ltd with a contract to provide unexploded ordnance (UXO) consultancy services covering zones in the Dutch North Sea identified in the Offshore Wind Energy Roadmap 2030. The tender covers six offshore wind zones, the 700MW Hollandse Kust Noord, the 700MW Hollandse Kust (

Hornsea One Ltd has agreed to pay out GBP 4.5 million to Ofgem for not remaining connected after the lightning strike in August 2019. To remind, the Hornsea Project One offshore wind farm suffered a reduction in the energy supply on 9 August due to a lightning strike. The 1.2GW wind farm immediately
Kitron has received orders from an undisclosed company to provide test systems and electronics modules for high-voltage direct current (HVDC) technology used for offshore wind. The Norwegian company will develop test systems and produce electronics modules that are part of control systems for HVDC t
Trianel Windkraftwerk Borkum has issued a tender for the replacement of defective inter-array cables at the Trianel Windpark Borkum offshore wind farm in Germany. The subject of the contract is the replacement of defective inter-array cables between turbines and/or the offshore substation, including
The European Investment Bank (EIB) has approved funding for the Tennet South-West 380KV West grid project in the Netherlands. EIB will provide around EUR 250 million in funding for the project valued at around EUR 509 million. The TenneT South-West 380KV West comprises the construction of the electr
The project will be built off Nissum Fjord in the North Sea and is expected to feature 13-15MW turbines set to be operational between 2024 and 2027.
Ofgem has selected Transmission Capital Partners as the preferred bidder for the offshore transmission assets of the Beatrice offshore wind farm in Scotland. Transmission Capital Partners, a consortium comprising INPP, Amber Infrastructure and Transmission Investment, expects to invest up to GBP 60
Balfour Beatty has won a contract to deliver the British onshore civil works for the Viking Link interconnector, the first high-voltage direct-current (HVDC) link between Great Britain and Denmark. Under the GBP 90 million four-year contract, Balfour Beatty is responsible for the civil engineering a
DEME Group has completed the pull-in of two export cables of the SeaMade offshore wind project into Elia’s Offshore SwitchYard (OSY) platform. DEME’s cable-laying vessel Living Stone picked up the export cables for the 487MW project from Hellenic Cables’ facility in Soussaki, Greece, in mid-November