Digital radio products designer and supplier Sepura has been selected to provide a complete communications solution for an undisclosed offshore wind farm located off the coast of Germany. The wind farm will be equipped with a TETRA system, featuring a number of base stations, Sepura’s SC20 series ha
The installation of scour protection around the 51 foundations of the Nobelwind (Bligh Bank II)offshore wind project finished yesterday, 8 June. The erosion protection consists of a light filter layer (first phase) and a heavier coating layer specifically designed for various locations and water dep
Vattenfall has chosen A2SEA to install MHI Vestas V164-8.0MW turbines at the 400MW Horns Rev 3 offshore wind farm. Starting in summer 2018, A2SEA will deploy its offshore installation vessel, Sea Installer, to install the turbines. The turbines will be loaded out of the port of Esbjerg. ”As pioneers
Twenty-four monopiles have been installed at the Veja Mate offshore wind farm, thus crossing a milestone of having one third of its 1300T monopiles in their respective positions. The construction phase began in April 2016, and the contractor Offshore Wind Force (OWF) has managed to install 24 monopi
Walcon Marine has completed berthing facilities at Great Yarmouth for vessels supporting the build and future maintenance of the 402 MW Dudgeon offshore wind farm. This forms part of the infrastructure of the purpose-built Operations & Maintenance base for the wind farm, which will provide 24/7 acce
The Netherlands-based consultancy Tauw Group will carry out soil investigations and determine the most suitable route for onshore cables which will connect four 350MW offshore wind farms in the Hollandse Kust (zuid) zone to the Dutch grid, TenneT reports. Tauw will examine several onshore cable rout
GE Renewable Energy has shared a photo showing offshore wind towers for the 30MW Block Island wind farm being arranged in a line in Providence after completing their journey from Europe to Rhode Island, US. The five-turbine offshore wind farm is being developed by Deepwater Wind some three miles off
Windwave Workboats has sent its 18-metre Wind Farm Support Vessel (WFSV) Freddie S to Grimsby to start a new role providing 24-hour jack-up support for Siemens Wind Power Service on the Westermost Rough wind farm. Freddie S will be supporting a team of Siemens’ heavy lift technicians who are working
EDF Energy Renewables will utilise the Port of Blyth as a mobilisation and operation & maintenance base for its new offshore wind farm to be installed off the coast of Northumberland. Port of Blyth Chief Executive Martin Lawlor said: “We’re delighted to be providing both an operational and mobilisat
Siem Offshore Contractors GmbH ( SOC) has started laying the first inter-array cable in the construction area of the 332MW Nordsee One offshore wind farm. The wind farm’s 54 6.15MW turbines will be connected to the offshore substation by ten strings of cables with an overall length of approximately
Seaway Heavy Lifting’s crane vessel, Stanislav Yudin, installed the offshore accommodation platform for the 288MW DanTysk offshore wind farm some 90 kilometres off the German North Sea coast today at 4 AM CET. The platform stands 20 metres above sea level and will house up to 50 people in a space of
Specialist explosive ordnance disposal contractor Ramora UK is preparing to undertake a programme of disposal of items previously identified as unexploded wartime ordnance, found on the seabed where the 336MW Galloper wind farm will be built off the Suffolk coast. The bombs were identified during su
Taipower has signed a contract with NIRAS and Sinotech as advisors for a new Taiwanese wind farm of up to 100MW. In a joint venture, the companies will provide client advice for Changhua Offshore Wind Farm, for which the construction is due to begin in 2018. The wind farm will have a capacity of abo
Adverse sea conditions have pushed back the installation of the 20-mile National Grid submarine cable from Narragansett, Rhode Island, to Block Island by one week. The cable laying barge Big Max was initially scheduled to install the cable last week, however, rough sea conditions postponed the works