MHI Vestas Offshore Wind has received an order from EDF Energy Renewables for five V164-8.0 MW turbines to be installed at the 41.5 MW Blyth Offshore Demonstrator Project. The V164-8.0 MW turbines – rated with a capacity of 8MW – have been optimised for the project, utilising a power mode to be able
VBMS has been awarded a contract by EDF Energy Renewables to provide the subsea connection between the offshore turbines and the onshore grid for the Blyth offshore wind farm. The scope of work for VBMS includes the supply and installation of a total of approximately 14 kilometres of export and inte
EDF Energy Renewables will build a new offshore wind farm off the coast of Blyth in Northumberland. Onshore construction work has already begun and offshore work will start in 2017. The wind farm will comprise five turbines, totaling 41.5MW in capacity. The project has permission for a maximum total
The official inauguration of Vattenfall’s Kentish Flats Extension (KFE) offshore wind farm is being held today, with the ceremonial ribbon cut on board the MV Balmoral, 7km off Herne Bay and Whitstable. Vattenfall is ahead on the low cost energy challenge, according to Gunnar Groebler, Vattenfall’s
Danish national transmission system operator Energinet.dk has started works to install a 33-kilometre subsea cable which will connect the offshore substation at the 400MW Horns Rev 3 offshore wind farm to the power grid on land. JD Contractor’s multipurpose offshore installation vessel Sima will ins
Dredger Mimar Sinan and the split hopper barge Tiger have started work at the Tahkoluoto offshore wind farm site. The vessels are working on dredging and excavation for foundations and cable ditches. The underground cable and substation will be installed by the next summer, with foundations and subs
Vattenfall is getting ready to inaugurate the 49.5MW Kentish Flats Extension offshore wind farm on the southern side of the Outer Thames Estuary at noon local time today. The wind farm comprises 15 MHI Vestas V112 3.3MW turbines and is located next to the 90MW Kentish Flats offshore wind farm which
UK-flagged cable laying vessel, Cable Enterprise, has today started installing a section of the 90-kilometre Ostwind 1 offshore cable system which will connect the 385MW Arkona and the 350MW Wikinger offshore wind farms in the German part of the Baltic Sea to an onshore substation in Lubmin, 50Hertz
Installation works on the 402MW Dudgeon offshore wind farm are progressing according to plan and the project is halfway to being completed, according to Dudgeon Offshore Windfarm Limited (DOWL). The wind farm’s export cables were laid and the jacket for the offshore substation was installed in May.
Tekmar Energy, a cable protection systems specialist (CPS) for offshore wind farms, has recently been awarded a contract with DONG Energy to supply 184 of its TekLink CPS on the 660MW Walney Extension offshore wind farm. This comes after Tekmar’s previous involvement in the Walney 1 and Walney 2 pro
Hollandia Offshore B.V. and the Danish transmission system operator, Energinet.dk, signed a contract for the engineering, procurement and commissioning of the Kriegers Flak substations on 31 May. The project comprises two unmanned substations which are due for delivery to the installation site in Ap
Shell Setting Up ‘New Energies’ Unit. Oil & Gas Companies to Cause Clash of Giants in Offshore Wind? Shell has created a new division called New Energies, through which the oil and gas giant will invest in wind energy, along with its hydrogen, biofuels and electrical activities, according to The Gua
MHI Vestas Offshore Wind and Vattenfall have signed a contract for the supply V164-8.0 MW turbines to Denmark’s 400 MW Horns Rev 3 project, which is set to produce the world’s cheapest offshore wind power, the turbine maker said. The contract was signed following Vattenfall’s announcement of the fin
Engie Fabricom and Iemants completed the load-out of the topside for the 258MW Burbo Bank Extension offshore wind farm at the ENGIE Fabricom’s Hoboken yard on 30 May. The 1180-tonne topside was placed next to the 985-tonne offshore substation jacket on the pontoon. The jacket was loaded onto the pon