Ecowende, a joint venture between Shell and Eneco, has placed an order for 52 Vestas V236-15.0 MW wind turbines for the Hollandse Kust West VI offshore wind farm, located about 53 kilometres off the Dutch coast, near IJmuiden. Turbine installation at sea is expected to begin in the second quarter of

Shortly after changing the preferred wind turbine supplier, the three projects in the Norfolk Offshore Wind Zone in the UK have now also changed hands as RWE will acquire Vattenfall’s 4.2 GW Norfolk portfolio for GBP 963 million (approximately EUR 1.1 billion). The new owner says it will also resume

TotalEnergies has decided to sell a 25.5 per cent equity stake in Seagreen, Scotland’s largest offshore wind farm, in a GBP 522 million (about EUR 602 million) deal with Thailand’s national oil and gas company PTTEP. Following this farm down, TotalEnergies retains 25.5 per cent of Seagreen, alongsid

Vattenfall has signed agreements with Vestas for three large-scale offshore wind projects in the Norfolk Zone, UK, where the developer plans to use the new V236-15 MW wind turbines. This marks a switch in the wind turbine model planned for the projects as the developer first named Siemens Gamesa as

Ørsted has taken the final investment decision (FID) on what the company says is the world’s single largest offshore wind farm, the 2.9 GW Hornsea 3, which is expected to be completed around the end of 2027. In July 2022, Ørsted was awarded a contract for difference (CfD) for Hornsea 3 at an inflati

Ecowende and Sif Holding will collaborate on the construction of Ecowende’s offshore wind farm Hollandse Kust West site VI, located about 53 kilometres off the Dutch coast, near IJmuiden. The collaboration for this project between the offshore wind farm developer, a joint venture of Shell and Eneco,

Van Oord has completed the installation of all foundations and inter-array cables at Iberdrola’s Baltic Eagle offshore wind farm in the German sector of the Baltic Sea. The heavy-lift installation vessel Svanen installed the final monopile in September and the company has now put all the transition

The Hollandse Kust Noord offshore wind farm, built by CrossWind, a joint venture between Shell and Eneco, went into operation on 20 December. After final commissioning, the offshore wind farm will add 759 MW of generation capacity to the Dutch electricity grid and achieve the 4.5 GW offshore wind ta

The Sceirde Rocks Windfarm, developed by Irish Fuinneamh Sceirde Teoranta (FST), a joint venture owned by Corio Generation and global infrastructure investor, Ontario Teachers’ Pension Plan, has completed geophysical and metocean surveys that will inform its forthcoming planning application. The sur

Swedish company Eolus Vind has submitted an application for the Najaderna offshore wind project outside Tierp, Sweden with a planned capacity of 1 GW-1.7 GW. The fixed-bottom Najaderna offshore wind project is located approximately 17 kilometres off the coast within Tierp municipality in Uppsala Cou

Boskalis’ DP installation vessel Bokalift 1 has installed the first offshore substation platform (OSP) at the Moray West offshore wind farm site in Scotland. The heavy lift operations in the Port of Nigg and on-site were completed safely and successfully, according to the developer Ocean Winds. As o

All 62 wind turbines have been installed at the Saint-Brieuc offshore wind farm in France, developed by Ailes Marines, a 100 per cent subsidiary of Iberdrola. The first wind turbine was installed in May on position number SB44, located in the northern part of the offshore construction site while the

The 288 MW Butendiek offshore wind farm situated in the German North Sea has secured a second long-term Power Purchase Agreement (PPA). Under the new agreement, BKW Energie AG, a Swiss energy utility, will purchase 18 per cent of the wind farm’s total production, equivalent to over 200 GWh annually,

Asso.subsea has completed the inter-array cable installation and protection operations for the 500 MW Fécamp wind farm offshore Normandy, France. Asso.subsea was contracted by Italy-headquartered Prysmian Group to execute the seabed preparation, installation, and protection works, involving four dif