Offshore grid operator TenneT has selected the Van Oord-Hellenic Cables consortium to connect the Hollandse Kust (South) Alpha and Beta offshore platforms to the Dutch onshore grid.
The 659MW Walney Extension offshore wind farm was officially opened on Thursday, 6 September, at a ceremony in Barrow in the north-west of England.
Seaway Heavy Lifting’s (SHL) vessel Stanislav Yudin has installed 16 out of 32 monopile foundations at the Trianel Windpark Borkum II in the German North Sea.
The New Jersey Board of Public Utilities has officially accepted the application tendered by EDF Renewables and Fishermen’s Energy for the Nautilus Offshore Wind project.
US offshore wind developer Vineyard Wind has submitted a Supplemental Draft Environmental Impact Report (SDEIR) to the Massachusetts Environmental Policy Act Office (MEPA) for the 800MW Vineyard Wind project offshore Massachusetts.
The Tahkoluoto offshore wind farm in Finland, the world’s first built for icy conditions, has marked one year since inauguration.
NKT has commissioned the high-voltage cable system on the 659MW Walney Extension offshore wind farm in the Irish Sea.
The first of the 31 monopile foundations has been installed on Northland Power’s 269MW Deutsche Bucht offshore wind farm in the German North Sea.
The jack-up vessel Seajacks Scylla has left Cuxhaven loaded with the first three monopiles and transition pieces to be installed on the 269MW Deutsche Bucht wind farm in the German North Sea.
Fred. Olsen Windcarrier’s jack-up installation vessel Bold Tern installed the final MHI Vestas 8MW turbine on Ørsted’s Borkum Riffgrund 2 wind farm on Friday, 31 August, completing the project ahead of schedule.
Triton Knoll has agreed a Memorandum of Understanding (MoU) with Associated British Ports (ABP) to use its Grimsby facility as the Triton Knoll wind farm’s long-term Operations and Maintenance (O&M) base.
A2Sea’s jack-up vessel Sea Installer has completed the installation of all 42 turbines at the Rentel offshore wind farm in Belgium.
Equinor and its partners in the Snorre and Gullfaks licences have secured a portion of funding necessary for the project to power these two oil and gas fields on the Norwegian continental shelf with floating offshore wind turbines.
Ørsted and innogy have entered a power purchase agreement (PPA) under which Ørsted will offtake 100% of the power generated by the Triton Knoll offshore wind farm, for which innogy has now reached financial close.